Texas AI Docket

Batch Zero, and the calendar with a hole in it

Published August 19th 8 slides

The deck

Slide 1 of 8Slide 2 of 8Slide 3 of 8Slide 4 of 8Slide 5 of 8Slide 6 of 8Slide 7 of 8Slide 8 of 8

The story

August 7th came and went.

The directive landed on August 3rd. ERCOT's own Batch Zero classification date passed 12 days ago.

Four days of warning.

"ERCOT will not notify each Interconnecting Distribution Service Provider and Transmission Service Provider of how any Large Load is classified in the Batch Zero Interconnection Study by August 7, 2026"

ERCOT gave 4 days of notice before its own classification date. The letter has stood 16 days.

No service provider was to be told by the 7th.

No service provider was to be told how any large load was classified by August 7th.

Three figures, two documents.

Each figure is its source's own wording. None may be multiplied by another.

One office. The same day. Two wordings.

"The PUCT and ERCOT must complete this audit before any data center project moves forward."
"before any additional data centers are approved to move forward"

The marked words are where the letter narrows what the release says. The letter's condition is on approvals. The release's condition is on all forward movement. Both are on the record and they are not interchangeable.

The Governor's office said the Data Center Coalition will comply.

"I established clear guardrails to ensure data centers protect our electric grid, conserve our water, respect our neighborhoods, and pay their own way ..."

The Coalition is the sector's membership body. Said on August 18th by the Governor's office, about the standards that office set rather than a measured result.

"One data center that could not comply chose to end operations before even beginning construction."

What is still open to you.

Open meeting. ERCOT said it would file for a good cause exception ahead of it.

A second open meeting, on the commission's own calendar.

Public comment deadline, on the commission's own calendar. No docket is named against it.

The proposed rule on Large Load Demand Management Service. It took a comment on August 18th.

The record entry for this decision is Governor Abbott directs the utility commission and ERCOT to audit every data center in the interconnection queue before any advances.

What was verified

21 claims, each re-fetched from its source before this deck shipped.

  1. ERCOT recorded receiving Governor Abbott's directive letter on August 3rd, 2026, ordering a verification process before any data center Large Load advances through interconnection.

    Today, August 3, 2026, Electric Reliability Council of Texas, Inc. (ERCOT) received a letter from Governor Greg Abbott directing ERCOT to conduct a verification process before advancing any data center Large Loads through the interconnection process.

    PRIMARY ERCOT Market Notice M-A080326-01, Update Regarding Batch Zero Timelines and Processes · checked August 19th

  2. The directive stopped ERCOT's Batch Zero clock. ERCOT stated it would not tell service providers how any Large Load was classified in the Batch Zero Interconnection Study by the August 7th, 2026 date.

    ERCOT will not notify each Interconnecting Distribution Service Provider and Transmission Service Provider of how any Large Load is classified in the Batch Zero Interconnection Study by August 7, 2026

    PRIMARY ERCOT Market Notice M-A080326-01, Update Regarding Batch Zero Timelines and Processes · checked August 19th

  3. ERCOT said it would seek a good cause exception from the Batch Zero timelines in Planning Guide Sections 5 and 9. The filing was to come ahead of the Public Utility Commission's August 20th, 2026 open meeting.

    ERCOT will file, in advance of the Public Utility Commission of Texas's (PUCT's) August 20, 2026 open meeting, a request for a good cause exception related to the timelines and process for Batch Zero set forth in ERCOT Planning Guide Sections 5 and 9.

    PRIMARY ERCOT Market Notice M-A080326-01, Update Regarding Batch Zero Timelines and Processes · checked August 19th

  4. ERCOT committed to updating the market notice once the good cause exception filing reached the Public Utility Commission.

    ERCOT will update this Market Notice once the filing has been made with the PUCT.

    PRIMARY ERCOT Market Notice M-A080326-01, Update Regarding Batch Zero Timelines and Processes · checked August 19th

  5. ERCOT filed the pause as Market Notice M-A080326-01, under the subject line Update Regarding Batch Zero Timelines and Processes.

    Update Regarding Batch Zero Timelines and Processes

    PRIMARY ERCOT Market Notice M-A080326-01, Update Regarding Batch Zero Timelines and Processes · checked August 19th

  6. Abbott's letter puts the interconnection queue at approximately 474 gigawatts of requests to connect to the Texas grid.

    is currently considering approximately 474 gigawatts of requests to connect to the Texas grid

    PRIMARY The Governor's signed directive letter to the PUCT and ERCOT · checked August 19th

  7. The Governor's press release describes the same queue as approximately over 474 gigawatts, a wording the signed letter does not use.

    currently considering approximately over 474 gigawatts of requests to connect to the Texas grid

    PRIMARY Office of the Governor press release, Governor Abbott Directs Comprehensive Data Center Audit · checked August 19th

  8. The letter states that approximately 90 percent of the new power requests are data centers.

    Approximately 90 percent of the new power requests are data centers.

    PRIMARY The Governor's signed directive letter to the PUCT and ERCOT · checked August 19th

  9. The queue is described as more than five times Texas' record peak electricity demand for ERCOT.

    more than five times Texas' record peak electricity demand for ERCOT

    PRIMARY Office of the Governor press release, Governor Abbott Directs Comprehensive Data Center Audit · checked August 19th

  10. On August 3rd, 2026, Abbott directed the PUCT and ERCOT to run a comprehensive verification and audit of every data center advancing through ERCOT's interconnection process.

    Governor Greg Abbott today directed the Public Utility Commission of Texas (PUCT) and the Electric Reliability Council of Texas (ERCOT) to conduct a comprehensive verification and audit of all data centers advancing through ERCOT's interconnection process.

    PRIMARY Office of the Governor press release, Governor Abbott Directs Comprehensive Data Center Audit · checked August 19th

  11. The audit is a gate rather than a study. No data center project moves forward until it is complete, and a project that fails the requirements is denied connection to the grid.

    The PUCT and ERCOT must complete this audit before any data center project moves forward. Any project that fails to comply with the requirements set forth by the PUCT and ERCOT will be denied connection to the Texas grid.

    PRIMARY Office of the Governor press release, Governor Abbott Directs Comprehensive Data Center Audit · checked August 19th

  12. The signed letter words the gate more narrowly than the press release does, halting approvals rather than all forward movement.

    before any additional data centers are approved to move forward

    PRIMARY The Governor's signed directive letter to the PUCT and ERCOT · checked August 19th

  13. Abbott grounds the audit in data centers failing to answer the commission's existing survey of water and power usage required under the General Appropriations Act.

    survey measuring water and power usage under the General Appropriations Act makes this necessary

    PRIMARY The Governor's signed directive letter to the PUCT and ERCOT · checked August 19th

  14. The directive requires each project to disclose every tax incentive, grant and abatement it has received or expects to receive.

    That would include all state and local tax incentives, grants, abatements, or other public financial assistance received or expected to be received

    PRIMARY Office of the Governor press release, Governor Abbott Directs Comprehensive Data Center Audit · checked August 19th

  15. The directive requires each project to say whether it brings and reuses its own water or draws water local communities need.

    The extent to which data centers are bringing their own water and reusing their own water as opposed to using water needed by local communities.

    PRIMARY Office of the Governor press release, Governor Abbott Directs Comprehensive Data Center Audit · checked August 19th

  16. On August 18th, 2026, the Governor's office said the Data Center Coalition, the sector's membership body, will comply with his data center standards.

    the Data Center Coalition, the data center sector's membership coalition, will comply with the standards and guidelines he established for data centers

    PRIMARY Office of the Governor press release, Data Center Coalition Commits To Comply · checked August 19th

  17. The August 18th release states that one data center could not comply and ended operations before construction began. The release does not name it.

    They are being universally implemented by data centers across the state. One data center that could not comply chose to end operations before even beginning construction.

    PRIMARY Office of the Governor press release, Data Center Coalition Commits To Comply · checked August 19th

  18. Abbott framed the guardrails around four demands on data centers, the grid, water, neighborhoods and paying their own way.

    I established clear guardrails to ensure data centers protect our electric grid, conserve our water, respect our neighborhoods, and pay their own way,

    PRIMARY Office of the Governor press release, Data Center Coalition Commits To Comply · checked August 19th

  19. The commission's calendar lists an open meeting on Friday, August 21st, 2026, the day after the meeting ERCOT named.

    Open Meeting - Friday, August 21, 2026

    PRIMARY The Public Utility Commission's own calendar feed · checked August 19th

  20. The commission's calendar lists a public comment deadline on Friday, September 4th, 2026.

    Public Comment Deadline - Friday, September 4, 2026

    PRIMARY The Public Utility Commission's own calendar feed · checked August 19th

  21. Project 58482, the proposed rule on Large Load Demand Management Service, took a comment on August 18th, 2026 from Modern Tex Consulting.

    Comments of Modern Tex Consulting LLC on Performance Reporting and Evaluation Under Proposed 16 TAC § 25.521

    PRIMARY PUCT Interchange, the filing list for Project 58482 · checked August 19th

Beats

data-centers

Every article