Alamo Data Center

A data center site in Red Oak with Google named as operator and a local property entity as owner. City records place the project at a highway corner and show years of zoning work, but they do not disclose delivered load or an operating date.

8Sourced facts4Source records5Open gaps

What the record establishes

Owner of record
Alamo Mission LLC[1]registry read August 27th, 2026
Occupant of record
Design LLC[1]registry read August 27th, 2026
Operator of record
Google LLC[1]registry read August 27th, 2026
Location
Northwest corner of East Ovilla Road and State Highway 342, Red Oak, Ellis County[2]
First city approvals described in the budget record
July 2019[4]
Later zoning case
Planned Development 66 Revised 4[3]as of January 3rd, 2023
Current zoning request
Planned Development 66 Revised 7[2]as of February 9th, 2026
Property records named in the current request
4 units[2]

What changes the reading

  • The legal roles matter here. Google is the operator in the state registry, while Design is the occupant and Alamo Mission is the owner. Those names should not be collapsed into one company.[1]
  • The city described this as a data center site when the first local approvals were granted.[2][3][4]
  • The current zoning request still describes the property as a data center complex.[2][3][4]
  • A zoning approval establishes what a property may be used for. It does not establish the amount of equipment installed, the load served or the date customer operations began.[2][3]

Still not public

  • Building count, square footage and acreage are not public in the records read here.
  • Critical information technology capacity and measured demand are not public.
  • The date operations began is not public.
  • Cooling design and measured water use are not public.
  • The relationship between Design and Google at this site is not explained.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. Red Oak City Council Regular Meeting AgendaCity of Red Oaklocal governmentRead August 27th, 2026.
  3. Red Oak Planning and Zoning Commission AgendaCity of Red Oaklocal governmentRead August 27th, 2026.
  4. City of Red Oak Budget DocumentCity of Red Oaklocal governmentRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.