AUS 01 02 03 Data Center
The first numbered facilities inside Prime Data Centers' planned Lockhart campus. County and state records tie the registry owner to the physical site, while campus figures remain broader than the three facilities named here.
18Sourced facts4Source records5Open gaps
What the record establishes
- Planned critical information technology load for the full campus
- 384 MW[3]
- Planned buildings across the full campus
- 8 buildings[3]
- Full campus site area
- 205 acres[3]
- Planned full campus building area
- 2,000,000 sq ft[3]
- First listed building critical load
- 144 MW[3]
- First listed building area
- 250,000 sq ft[3]
- Filed cost for the first two shell buildings
- $400 million[4]
- Filed area for the first two shell buildings
- 760,000 sq ft[4]
- County agreement site area
- 205.756 acres[2]
- Filed address
- 1395 Bob White Road, Lockhart[4]
- Current company campus address
- 3300 FM 2720, Lockhart[3]as of August 27th, 2026
- Filed construction window
- June 1st, 2026 through September 30th, 2027[4]
- Electric utility named by the developer
- Bluebonnet Electric Cooperative with an onsite substation[3]
- Cooling design stated by the developer
- Closed loop air and liquid cooling[3]
- Owner of record
- Lockhart Property LLC[1]registry read August 27th, 2026
- Occupant of record
- Paile LLC[1]registry read August 27th, 2026
- Operator of record
- Lockhart Property LLC[1]registry read August 27th, 2026
- Certification effective
- August 17th, 2026[1]
What changes the reading
- The county agreement names Lockhart Property as developer and uses Prime's first Austin campus code. That exact company bridge connects the registry entry to Prime's Lockhart campus.[1][2][3]
- Prime's load, acreage, building count and floor area describe the full campus. The registry entry names only the first three numbered facilities, so the full campus figures are not assigned to those facilities alone.[1][3]
- The building filing covers the first two shells. Its cost and area do not describe the third facility named in the registry certification.[1][4]
- The building filing leaves the tenant field blank while the later registry names Paile as occupant. A blank filing field does not contradict the current registry role.[1][4]
- The filed and current company addresses differ. Both are retained because the public sources do not say whether the change reflects an entrance, parcel or address update.[3][4]
Still not public
- The load and building area of the third facility are not public.
- Delivered power and actual electrical demand are not public.
- Construction progress and an opening date are not established.
- The relationship between Paile and any outside computing customer is not public.
- Expected water use and backup generation are not public.
Source trail
- Data Center ListsTexas Comptroller of Public Accounts
- Prime Data Centers Development AgreementCaldwell County
- Prime Data Centers Austin CampusPrime Data Centers
- Prime Data Center AUS First Building FilingTexas Department of Licensing and Regulation
The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.