Borden County Data Center
An SB Energy artificial intelligence campus in early construction. County records give unusually concrete first phase power and water estimates, while the company presents a larger long term site that remains a plan.
10Sourced facts3Source records5Open gaps
What the record establishes
- First phase gross capacity
- 250 MW[2]
- First phase information technology load
- 214 MW[2]
- Long term site capacity above
- 1 GW[3]
- Building phases described by the county
- 5 buildings[2]
- Cooling design described by the county
- Closed loop system described as requiring 0 gallons per day of makeup process water[2]
- Employee water estimate for each building phase
- less than 4,000 gallons per day for drinking and toilets[2]
- Employee water estimate if every phase is built
- about 20,000 gallons per day for drinking and toilets[2]
- Company status
- Early construction[3]as of August 27th, 2026
- Owner, occupant, and operator of record
- Borden County DC, LLC[1]as of August 27th, 2026
- Certification effective
- November 11th, 2025[1]
What changes the reading
- The county figures describe the first phase and a possible full build. The larger company figure belongs to the long term campus and is not delivered capacity.[2][3]
- The water figures are developer estimates repeated by the county. They concern process makeup water and employee use, not measured withdrawals after operation begins.[2]
- The certification lists one project company in every legal role and does not name an outside computing customer. SB Energy identifies itself as the campus developer but does not name a tenant on its project page.[1][3]
- Early construction is the developer's current status. It does not establish that the first building or its electrical service is complete.[3]
Still not public
- The exact street address and campus acreage are not public.
- An outside computing customer has not been named.
- Delivered power and actual electrical demand are not public.
- A first building completion date has not been established.
- Measured water use and the source of employee water are not public.
Source trail
- Data Center ListsTexas Comptroller of Public Accounts
- Borden County Data Center Questions and AnswersBorden County
- SB Energy Data CentersSB Energy
The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.