Borden County Data Center

An SB Energy artificial intelligence campus in early construction. County records give unusually concrete first phase power and water estimates, while the company presents a larger long term site that remains a plan.

10Sourced facts3Source records5Open gaps

What the record establishes

First phase gross capacity
250 MW[2]
First phase information technology load
214 MW[2]
Long term site capacity above
1 GW[3]
Building phases described by the county
5 buildings[2]
Cooling design described by the county
Closed loop system described as requiring 0 gallons per day of makeup process water[2]
Employee water estimate for each building phase
less than 4,000 gallons per day for drinking and toilets[2]
Employee water estimate if every phase is built
about 20,000 gallons per day for drinking and toilets[2]
Company status
Early construction[3]as of August 27th, 2026
Owner, occupant, and operator of record
Borden County DC, LLC[1]as of August 27th, 2026
Certification effective
November 11th, 2025[1]

What changes the reading

  • The county figures describe the first phase and a possible full build. The larger company figure belongs to the long term campus and is not delivered capacity.[2][3]
  • The water figures are developer estimates repeated by the county. They concern process makeup water and employee use, not measured withdrawals after operation begins.[2]
  • The certification lists one project company in every legal role and does not name an outside computing customer. SB Energy identifies itself as the campus developer but does not name a tenant on its project page.[1][3]
  • Early construction is the developer's current status. It does not establish that the first building or its electrical service is complete.[3]

Still not public

  • The exact street address and campus acreage are not public.
  • An outside computing customer has not been named.
  • Delivered power and actual electrical demand are not public.
  • A first building completion date has not been established.
  • Measured water use and the source of employee water are not public.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. Borden County Data Center Questions and AnswersBorden Countylocal governmentRead August 27th, 2026.
  3. SB Energy Data CentersSB EnergycompanyRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.