Texas AI Docket

Texas data centers Every registered facility.

Certified facility dossier

Cyrusone LLC - Houston West III Data Center

A Houston building the registry certifies under CyrusOne with Meta subsidiary Paile as occupant. DataBank bought the Houston portfolio later that year and now markets this address as HOU three, so the public identity has changed since certification.

14Sourced facts5Source records4Open gaps

What the record establishes

Owner of record
Cyrusone LLC[1]registry read August 27th, 2026
Occupant of record
Paile LLC[1]registry read August 27th, 2026
Operator of record
Cyrusone LLC[1]registry read August 27th, 2026
Address
11003 Corporate Centre Drive, Houston, Harris County[2]
Filed fitout cost
$45.6 million[2]
Filed fitout area
200,000 sq ft[2]
Current DataBank name
HOU3[3]as of August 27th, 2026
Current information technology floor area
41,860 sq ft[3]as of August 27th, 2026
Current critical information technology capacity
6.5 MW[3]as of August 27th, 2026
Onsite carriers listed by DataBank
39 units[3]as of August 27th, 2026
Houston portfolio acquisition price
$670 million[4]as of November 15th, 2022
Facilities in the Houston acquisition
4 facilities[4]as of November 15th, 2022
Power across the acquired Houston portfolio
42.5 MW[4]as of November 15th, 2022
Paile parent company
Meta Platforms, Inc.[5]as of December 31st, 2024

What changes the reading

  • The latest registry read still names CyrusOne even though DataBank says it acquired and migrated West three in the same year. The records disagree on the current owner and operator.[1][4]
  • Meta's subsidiary exhibit identifies Paile without naming this facility. The registry makes the facility link by placing Paile in the occupant role.[1][5]
  • The construction area covers a broad fitout scope. DataBank's smaller figure is information technology floor, so the two areas should not be treated as a conflict.[2][3]
  • The published critical capacity belongs to the building. It is not Paile's measured use, and the portfolio power figure covers four Houston facilities together.[3][4]

Still not public

  • Paile's occupied share and current load are not public.
  • The current legal owner and operator are not reconciled with the tax registry.
  • Water use is not public.
  • The public record does not say whether the original fitout scope all served Paile.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. ZHU1 at CyrusOne Houston West ThreeTexas Department of Licensing and RegulationfilingRead August 27th, 2026.
  3. Westway Park Three Data CenterDataBankcompanyRead August 27th, 2026.
  4. DataBank Completes Migration of CyrusOne Houston Data Centers and CustomersDataBankcompanyRead August 27th, 2026.
  5. Meta Platforms List of SubsidiariesU.S. Securities and Exchange CommissionfilingRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.