Dory Creek LLC Data Center

A Bitdeer subsidiary operating on part of the former Alcoa property in Rockdale. The company reports substantial electrical capacity in use for cryptocurrency mining and is evaluating a move toward colocation or artificial intelligence, but that evaluation is not a committed conversion.

9Sourced facts3Source records5Open gaps

What the record establishes

Owner of record
Bitdeer Inc.[1]registry read August 27th, 2026
Occupant of record
Dory Creek LLC[1]registry read August 27th, 2026
Operator of record
Dory Creek LLC[1]registry read August 27th, 2026
Location
Rockdale, Milam County[2]
Electrical capacity in use
563 MW[2]as of March 31st, 2026
Additional capacity in planning
179 MW[2]as of March 31st, 2026
Site operating since
February 2019[2]
Original property lease
June 6th, 2018[3]
Current use described by the company
Cryptocurrency mining[2]as of March 31st, 2026

What changes the reading

  • The original lease covers land, buildings, improvements and a power delivery network on former Alcoa smelter property. It is the legal basis for the site rather than a record of current load.[3]
  • Bitdeer's current filing identifies Dory Creek as a subsidiary and reports the electrical capacity in use at Rockdale. That capacity is not the same as information technology load.[2]
  • The company is evaluating a transition from mining to colocation or artificial intelligence cloud use. No signed tenant or construction commitment for that transition is disclosed in the source read here.[2]

Still not public

  • Current information technology load and measured grid demand are not public.
  • The amount of the planned capacity that has entered construction is not public.
  • No colocation or artificial intelligence tenant has been announced.
  • Cooling design and measured water use are not public.
  • Current mining hardware count is not public.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. Bitdeer Annual ReportU.S. Securities and Exchange CommissionfilingRead August 27th, 2026.
  3. Alcoa Property Lease AgreementU.S. Securities and Exchange CommissionfilingRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.