ECX AUS11-16

An EdgeConneX Austin expansion represented by a six building registry name. Two large buildings at the same Cedar Creek address have entered the state accessibility record, while public filings for the remaining numbered buildings were not found.

12Sourced facts3Source records5Open gaps

What the record establishes

Building filings found
2 buildings[2]
Filed cost for building eleven
$700 million[2]
Filed area for building eleven
729,537 sq ft[2]
Filed cost for building twelve
$700 million[3]
Filed area for building twelve
729,537 sq ft[3]
Filed address
6682 FM 535, Cedar Creek[2]
Filed construction window for both buildings
June 30th, 2026 through December 31st, 2028[2]
Building description in each filing
1 story data center with an automatic sprinkler system[2]
Property owner in the building filings
Burr Computer Environment Inc.[2]
Owner of record
EdgeConnex MCN Austin Property 5, LLC[1]registry read August 27th, 2026
Occupant and operator of record
EdgeConnex MCN Austin Operations 5, LLC[1]as of August 27th, 2026
Certification effective
April 24th, 2026[1]

What changes the reading

  • The registry name spans six building numbers, while only the first two building filings in that sequence were found. The missing filings may not yet exist or may use different project names.[1][2][3]
  • Each found building carries the same filed area, cost and schedule. They are preserved as separate filings and are not summed into a campus total.[2][3]
  • The state building records and registry name different property entities. The public pages do not explain whether the building filing owner is a land seller, affiliate or older project record.[1][2][3]
  • The tenant fields in the building filings are blank. That is not evidence that the planned buildings lack a future customer.[2][3]

Still not public

  • Planned information technology load and delivered power are not public.
  • A computing customer has not been named.
  • Public building filings for the later numbered structures were not found.
  • Cooling design and expected water use are not public.
  • Construction progress and an opening date are not established.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. EDCAUS11 Project DetailsTexas Department of Licensing and Regulationlocal governmentRead August 27th, 2026.
  3. EDCAUS12 Project DetailsTexas Department of Licensing and Regulationlocal governmentRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.