EDC AUSTIN, LLC

A planned Edged Energy campus near Maxwell with county agreements in place and one large building in the state accessibility record. The developer describes a closed loop design, but the campus is not treated here as complete or operating.

12Sourced facts4Source records5Open gaps

What the record establishes

Projected full campus improvements
$7.3 billion[2]
Original project tract
329.893 acres[4]
First development phase
127.328 acres[4]
Second development phase
192.608 acres[4]
Filed building cost
$2.8 billion[3]
Filed building area
869,684 sq ft[3]
Filed address
11255 Highway 142, Maxwell[3]
Filed construction window
June 1st, 2026 through June 30th, 2028[3]
Cooling design described to the county
Closed loop server cooling using a finite charge of nonpotable water[2]
Potable water use described to the county
Ordinary plumbing and food preparation[2]
Owner, occupant, and operator of record
EDC Austin, LLC[1]as of August 27th, 2026
Certification effective
January 9th, 2026[1]

What changes the reading

  • The county projection covers the wider campus. The state filing covers one building and should not be added to the campus projection as a separate commitment.[2][3][4]
  • The county approved development and tax agreements. Those approvals set terms for a planned project and do not prove that construction or electrical service is complete.[2][4]
  • The cooling description is a developer representation in county records. Measured water use will not exist until the system is built and operating.[2]
  • The building filing names Capital Land Investments as property owner, while the registry places the current data center roles with EDC Austin. The public records do not explain the property arrangement.[1][3]

Still not public

  • Planned information technology load and delivered power are not public.
  • A computing customer has not been named.
  • Backup generation and battery plans are not public.
  • The source and volume of the initial nonpotable water charge are not public.
  • A confirmed opening date is not public.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. April 2026 Commissioner Court RecapCaldwell Countylocal governmentRead August 27th, 2026.
  3. Edged Energy Austin Project DetailsTexas Department of Licensing and Regulationlocal governmentRead August 27th, 2026.
  4. April 9, 2026 Commissioners Court Agenda PacketCaldwell Countylocal governmentRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.