Certified facility dossier

EdgeConneX AU02

A CoreWeave certification tied to the second building on an EdgeConneX campus in Cedar Creek. A state filing shows a large new building under review, while a county agreement describes a broader four building plan.

11Sourced facts3Source records5Open gaps

What the record establishes

Filed construction cost
$440 million[2]
Filed building area
578,000 sq ft[2]
Buildings covered by the county agreements
4 buildings[3]as of December 9th, 2024
Permanent positions projected in each attached building application
50 jobs[3]
Address
8001 Wolf Lane, Building 2, 6752 FM 535, Cedar Creek, Bastrop County[2]
Filed work
New 2 story data center with site improvements[2]
Filed construction window
August 1st, 2025 through June 14th, 2026[2]
Owner of record
DFW33220N, LLC[1]registry read August 27th, 2026
Occupant of record
CoreWeave, Inc.[1]registry read August 27th, 2026
Operator of record
DFW33220N Operations 1, LLC[1]registry read August 27th, 2026
Certification effective
July 11th, 2025[1]

What changes the reading

  • The accessibility filing names the facility with the same campus code and legal owner used by the certification. Its completion date is a filed schedule, and review completion is not proof that the building opened.[1][2]
  • The county approved separate agreements for four buildings. The certification and accessibility filing concern one named building, so the broader campus count is not assigned to the occupant's space.[1][2][3]
  • The state project form left its tenant field unassigned. That blank does not override the later tax record naming CoreWeave, but neither record says how much of the building CoreWeave will use.[1][2]

Still not public

  • Delivered power and actual electrical demand are not public.
  • An opening or operating date has not been established.
  • The occupant's share of the building is not public.
  • Cooling design and measured water use are not public.
  • Final construction cost and completed floor area are not public.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. ECX Austin DFW33220N Project DetailsTexas Department of Licensing and Regulationlocal governmentRead August 27th, 2026.
  3. DFW33220N Building Tax Abatement AgreementsBastrop Countylocal governmentRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.