What the record establishes
- Campus area
- 5,769 acres[2]
- Stated power potential
- 11 GW[2]
- Stated AI floor area
- 18,000,000 sq ft[2]
- Phase one target
- 1.1 GW[2]
- Entities filed under this one certification
- 8 units[1]
- Location
- Amarillo, in the Texas Panhandle, next to the Department of Energy Pantex site[2]
- Project name
- Project Matador[2]
- Generation plan
- Federal application for 4 reactors using AP1000 technology, with gas and solar[2]
- Partner
- A lease with the Texas Tech University System[3]
What changes the reading
- Reading the entity list is the fastest way to understand this site. A turbine warehouse and a mobile generation entity are not things a colocation landlord files.[1]
- The nuclear reactors are at federal application stage. Nothing here says any of them is approved or built, and the phase dates are the company's own targets.[2]
Still not public
- No reactor is approved and the timeline is the company's own.
- Which buildings the single certification actually covers is not stated.
- Water sourcing for the campus is not public.
- Cooling design is not public.
Source trail
- Data Center ListsTexas Comptroller of Public Accounts
- Project Matador, Fermi America's Planned Power Campus in Amarillo, TexasConstruction Review Online
- Fermi America's lease with the Texas Tech University SystemAmarillo Tribune
The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.