Texas data centers Every registered facility.
Freestone Data Center
A planned artificial intelligence data center complex beside the existing Freestone Energy Center near Fairfield. State utility regulators approved a shared connection and net metering arrangement, while a separate building fitout has entered the accessibility record.
12Sourced facts3Source records5Open gaps
What the record establishes
- Planned data center load
- 760 MW[2]
- Existing colocated generation capacity
- 1,099 MW[2]
- Filed fitout cost
- $100 million[3]
- Filed fitout area
- 306,216 sq ft[3]
- Filed address
- 1360 FM 488, Fairfield[3]
- Filed fitout window
- August 23rd, 2026 through August 23rd, 2027[3]
- Grid arrangement approved by the state
- Shared point of interconnection and net metering with Freestone Energy Center[2]
- Distribution service provider
- Navarro County Electric Cooperative[2]
- Utility order date
- May 7th, 2026[2]
- Owner of record
- C1 Freestone 1, LLC[1]registry read August 27th, 2026
- Occupant and operator of record
- Paile, LLC[1]as of August 27th, 2026
- Certification effective
- March 24th, 2026[1]
What changes the reading
- The planned load belongs to the wider complex. The fitout filing covers one interior project and does not establish the capacity of that building.[2][3]
- The utility order approves a metering arrangement with operating conditions. It does not certify that the full data center load is built, energized or being served.[2]
- The existing gas plant and the planned data center share a connection under the approved design. That does not mean the data center will always be supplied only by the adjacent plant.[2]
- The building filing leaves its tenant field blank, while the registry names Paile as occupant and operator. A blank field is not evidence that no customer exists.[1][3]
Still not public
- Actual delivered load and the construction sequence are not public.
- A parent company and outside computing customer are not confirmed in the primary records.
- Cooling design and expected water use are not public.
- Backup generation and battery plans are not public.
- A confirmed opening date is not public.
Source trail
- Data Center ListsTexas Comptroller of Public Accounts
- Final Order in Docket 58872Public Utility Commission of Texas
- DFW20C Fitout Project DetailsTexas Department of Licensing and Regulation
The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.