Texas AI Docket

Texas data centers Every registered facility.

Certified facility dossier

Meitner Data Center

Google and Intersect Power's power first campus in the Texas Panhandle, built beside its own generation rather than drawing from the grid alone. It is air cooled by design, which in this part of the state is the whole point.

8Sourced facts3Source records4Open gaps

What the record establishes

Co-located wind, solar and battery storage, stated as more than
1 GW[3]as of June 4th, 2026
Texas Water Impact Fund
$10 million[3]as of June 4th, 2026
Caprock Workforce Hub site
800 acres[3]as of June 4th, 2026
Workforce hub capacity
3,500 workers[3]as of June 4th, 2026
Counties
Gray and Roberts Counties[2]
Nearest town
Pampa[3]
Cooling
Air cooling, with water limited to small scale domestic use[2]
Generation mix
Clean generation is planned from the first day. Onsite gas is intended for reliability.[3]

What changes the reading

  • Trade coverage has attached a headline investment figure and a data center load figure to this campus. Neither appears in Google's or Intersect's own announcements, so neither is published here.[2][3]
  • The registry owner is IP Meitner DTC, LLC, an Intersect Power affiliate, while the certified occupant is Google LLC. Alphabet has moved to acquire Intersect Power, which would put landlord and occupant under one roof.[1][3]

Still not public

  • Data center load in megawatts is not disclosed by either partner.
  • Total investment is not disclosed by either partner.
  • Building count and square footage are not disclosed.
  • Tax and school district agreements are not disclosed.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 21st, 2026.
  2. Google and Intersect to build Meitner Energy Center in TexasGooglecompanyRead August 21st, 2026.
  3. Google and Intersect Deepen Texas Roots with New Data Center and Energy Investments in Gray and Roberts CountiesIntersect PowercompanyRead August 21st, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.