Microsoft Corporation (SAT 15-17)

A three-building Microsoft campus on Westover Link. The certification groups the campus into one row, while construction and air records describe the buildings separately and show that they did not move through development at the same pace.

10Sourced facts5Source records4Open gaps

What the record establishes

Owner, occupant and operator of record
Microsoft Corporation[1]as of April 4th, 2023
Address
3555 Westover Link, San Antonio, Bexar County[3]
Buildings named in the certification
3 buildings[1]
SAT15 filed construction cost
$215.9 million[3]
SAT15 filed building area
245,000 sq ft[3]
SAT15 colocation facilities in the filing
5 units[3]
SAT16 filed construction cost
$215 million[4]
SAT16 filed building area
245,000 sq ft[4]
SAT16 colocation facilities in the filing
5 units[4]
Generator work in the air review snapshot
SAT15 in progress, SAT16 and SAT17 not installed[5]

What changes the reading

  • The air review treats Westover Link as a three-building campus. The construction register has separate filings for the first two buildings, while the same air review says equipment for the third had not been installed in its snapshot.[3][4][5]
  • Inspection complete on the first construction filing is an accessibility review status. It does not establish occupancy or service.[3]

Still not public

  • The current operating status of each building is not public.
  • The campus's information technology load is not public.
  • Water use and cooling design are not public.
  • A separate construction filing for the third building was not found.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. Westover Link datacenter construction updateMicrosoft LocalcompanyRead August 27th, 2026.
  3. Microsoft SAT15Texas Department of Licensing and RegulationfilingRead August 27th, 2026.
  4. Microsoft SAT16Texas Department of Licensing and RegulationfilingRead August 27th, 2026.
  5. Technical Review for Project 38510Texas Commission on Environmental QualitypermitRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.