Texas AI Docket

Texas data centers Every registered facility.

Certified facility dossier

Nexus Data Centers

A Hubbard campus that runs on its own gas turbines rather than on the grid. The registry shows the design before any coverage does, because it lists a power company for every building alongside the building itself.

8Sourced facts3Source records4Open gaps

What the record establishes

Filed power capacity
600 MW[2]
Permitted building area
491,000 sq ft[3]
Campus area
2,900 acres[2]
Stated campus ambition
7.7 GW[2]
Nexus entities in the registry
16 units[1]
Address
357 HCR 3372, Hubbard, Hill County[3]
Power design
Behind the meter, on site natural gas turbines, independent of the grid[2]
Construction window
January of 2026 to October of 2027[3]

What changes the reading

  • The registry pairs a power entity to each building entity, B one with power B one and so on. That pattern is visible in the state's list alone and it is exactly the behind the meter design the coverage describes. The filing structure gave away the business model.[1][2]

Still not public

  • The campus ambition figure is the developer's own and has no executed contract behind it here.
  • No tenant is named in the registry or in the coverage read.
  • Water use for the turbines and the halls is not public.
  • Which of the sixteen entities the single certification covers is not stated.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 21st, 2026.
  2. 600MW natural gas-powered data center campus proposed in Hubbard, TexasData Center Dynamicstrade pressRead August 21st, 2026.
  3. Nexus Data Centers Files Permit for a Data Center in Hubbard, TexasMLQ NewsdirectoryRead August 21st, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.