Texas data centers Every registered facility.
Poolside Data Center, Pecos County I
The certification that matters most on this page is the second one. Poolside held two for this Pecos County site, and the project behind them lost its anchor tenant. A certification records that the state granted an exemption. It is not evidence that a building exists or that anything is running in it.
10Sourced facts4Source records4Open gaps
What the record establishes
- Announced campus capacity
- 2 GW[2]
- Site area
- 568 acres[2]
- Anchor lease CoreWeave took, then terminated
- 250 MW[3]as of March 31st, 2026
- Capacity reserved for later expansion
- 500 MW[2]
- Nvidia GPUs planned from December of 2025
- 40,000 units[3]
- Location
- Longfellow Ranch, Pecos County, near Fort Stockton[2]
- Project name
- Project Horizon[2]
- Power design
- Behind the meter, beside a West Texas gas hub[2]
- First certification
- Phase one operations entity[1]as of October 23rd, 2025
- Second certification
- Phase two operations entity[1]as of March 6th, 2026
What changes the reading
- CoreWeave terminated its fifteen year anchor lease in the spring after Poolside's funding round failed to close. Trade coverage then described the campus as the most prominent failure in the Texas pipeline.[3][4]March 31st, 2026
- The state certified phase two of this site days before that termination was reported. Nothing in the registry has changed since. This is the clearest evidence on the site that a certification is a tax status rather than a building. It is why no page here says a facility is operating.[1][3]March 6th, 2026
Still not public
- Whether anything was built on the site is not established.
- Whether the certifications have been surrendered or lapsed is not public.
- Square footage and building count were never announced.
- The status of the second phase entity is not established.
Source trail
- Data Center ListsTexas Comptroller of Public Accounts
- Announcing Project Horizon, Why we're building a 2 gigawatt AI campus in TexasPoolside
- AI startup Poolside teams up with CoreWeave on 2GW data center in TexasData Center Dynamics
- How CoreWeave and Poolside Are Teaming Up in West TexasData Center Frontier
The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.