Certified facility dossier

Project Watertower

Yondr's planned Dallas area campus in Lancaster. A city incentive agreement sets minimum first phase commitments, while company materials describe a much larger multibuilding campus and a later power schedule.

13Sourced facts4Source records5Open gaps

What the record establishes

Capacity in the first company announcement
550 MW[3]
Minimum information technology capacity in the later sheet
500 MW[4]
Secured site area
163 acres[3]
Minimum first facility area under the city agreement
300,000 sq ft[2]
Minimum taxable value under the city agreement
$110 million[2]
Minimum full time equivalent jobs under the city agreement
30 jobs[2]
Minimum average annual wage under the city agreement
$80,000[2]
Total power shown in the later company sheet
828 MVA[4]
Initial utility allocation shown in the later sheet
150 MVA for December 2028[4]
Company ready for service target
Fourth quarter of 2028[4]
Owner of record
Redwood Dallas SPV, LLC[1]registry read August 27th, 2026
Occupant and operator of record
Yondr USA, LLC[1]as of August 27th, 2026
Certification effective
March 24th, 2026[1]

What changes the reading

  • The later company sheet presents a lower capacity floor than the earlier announcement. The two publications may reflect a design change or a different measure, so both are preserved.[3][4]
  • The city agreement sets thresholds for incentives. Its property, job and wage figures are commitments, not proof of completed investment or current employment.[2]
  • The initial utility allocation is only part of the later total power figure. It should not be presented as full campus service.[4]
  • The company schedule remains a target. The agreement also allows deadline changes when utility power is delayed.[2][4]

Still not public

  • The outside computing customer has not been named.
  • The number and sequence of planned buildings are not public.
  • Cooling design and expected water use are not public.
  • Backup generation and battery plans are not public.
  • The amount of power available beyond the initial allocation is not confirmed.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. Economic Development Performance Agreement with Redwood Dallas SPVCity of Lancasterlocal governmentRead August 27th, 2026.
  3. Yondr Secures Dallas Campus SiteYondr GroupcompanyRead August 27th, 2026.
  4. Dallas Campus Specification SheetYondr GroupcompanyRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.