Riot Corsicana Data Center I

Riot's active bitcoin mining campus near Corsicana and one of two newer state certifications at the site. Riot is planning a wider high density computing conversion, but public records do not assign a building or tenant to this numbered certification.

13Sourced facts5Source records5Open gaps

What the record establishes

Developed campus capacity
400 MW[2]as of June 30th, 2026
Expected full campus capacity
1 GW[2]as of June 30th, 2026
Prospective full campus information technology load
756 MW[4]as of April 30th, 2026
Location
Corsicana, Navarro County[3]
Campus interconnection
Direct 345 kV transmission connection[3]
Latest commercial status for the full campus
Under a nonbinding letter of intent with 1 tenant described as prospective[5]as of August 10th, 2026
Owner of record
Riot Platforms, Inc.[1]registry read August 27th, 2026
Occupant of record
Riot Platforms, Inc.[1]registry read August 27th, 2026
Operator of record
Riot Platforms, Inc.[1]registry read August 27th, 2026
Additional operator of record
RPI DC Master LLC[1]registry read August 27th, 2026
Additional operator of record
RPI Corsicana DC Holdings LLC[1]registry read August 27th, 2026
Additional operator of record
Riot Corsicana, LLC[1]registry read August 27th, 2026
Certification effective
December 12th, 2025[1]

What changes the reading

  • The developed campus figure includes existing bitcoin mining infrastructure. It is not delivered artificial intelligence load and should not be added to the prospective computing plan.[2][4]
  • The full campus capacity and prospective information technology load describe different measures. Both are planning context for the wider site rather than a load assigned to this certification.[2][4]
  • A nonbinding letter of intent is not an executed lease. Riot has not named the prospective Corsicana tenant.[5]
  • The public record does not publish parcel or building boundaries for Riot's overlapping Corsicana certifications. Campus facts are kept as context and are not treated as a measurement of this numbered record.[1][2][3]

Still not public

  • The physical boundary of this numbered certification is not public.
  • A computing tenant has not been named.
  • Delivered information technology load is not public.
  • Cooling design and expected water use for new computing space are not public.
  • A confirmed customer delivery date is not public.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. Riot Platforms Quarterly Report for JuneUnited States Securities and Exchange CommissionfilingRead August 27th, 2026.
  3. Corsicana CampusRiot PlatformscompanyRead August 27th, 2026.
  4. Riot First Quarter Investor PresentationUnited States Securities and Exchange CommissionfilingRead August 27th, 2026.
  5. Riot Second Quarter Investor PresentationUnited States Securities and Exchange CommissionfilingRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.