Riot Rockdale Data Center 1
The earlier of two current Riot certifications at Rockdale, tied to the company's first data center lease with AMD. Initial capacity has been delivered and more space is being built, while the larger frontier laboratory lease belongs to the later certification.
16Sourced facts4Source records5Open gaps
What the record establishes
- Initial AMD capacity delivered
- 25 MW[2]as of May 31st, 2026
- Additional AMD capacity contracted
- 25 MW[2]as of August 10th, 2026
- Total AMD capacity contracted
- 50 MW[2]as of August 10th, 2026
- Potential AMD capacity with remaining options
- 200 MW[3]
- Initial lease term
- 10 years[3]
- Land acquired with the first lease
- 200 acres[3]
- Developed Rockdale campus capacity
- 700 MW[4]
- Location
- Rockdale, Milam County[3]
- Latest AMD construction status
- Additional contracted capacity under construction[2]as of August 10th, 2026
- Owner of record
- Riot Platforms, Inc.[1]registry read August 27th, 2026
- Occupant of record
- Riot Platforms, Inc.[1]registry read August 27th, 2026
- Operator of record
- Riot Platforms, Inc.[1]registry read August 27th, 2026
- Additional operator of record
- Riot Rockdale Data Center 1[1]registry read August 27th, 2026
- Additional operator of record
- Riot Data Centers, LLC[1]registry read August 27th, 2026
- Additional operator of record
- Whinstone, US, Inc[1]registry read August 27th, 2026
- Certification effective
- November 18th, 2025[1]
What changes the reading
- Riot says the initial AMD capacity was delivered in late spring and the added capacity is under construction. Delivery does not disclose how much computing load AMD is actively using.[2]
- The larger potential AMD capacity depends on unexercised options. It is not contracted load and is kept separate from the current lease total.[2][3]
- The exact project company tied to Riot's later frontier laboratory lease appears only in the newer Rockdale certification. That later lease is therefore not assigned to this earlier record.[1][2]
- The developed campus figure includes bitcoin mining and multiple data center leases. It is wider site context rather than a load measurement for this certification.[2][4]
Still not public
- The physical boundary of this numbered certification is not public.
- AMD's active computing load is not public.
- Cooling design and expected water use for the leased space are not public.
- A completion date for the additional AMD capacity is not public.
- Backup generation and battery plans are not public.
Source trail
- Data Center ListsTexas Comptroller of Public Accounts
- Riot Second Quarter Results and Rockdale UpdateUnited States Securities and Exchange Commission
- Riot First Data Center Lease with AMDRiot Platforms
- Riot CampusesRiot Platforms
The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.