Riot Rockdale Data Center 2
The Rockdale project company tied by a securities filing to Riot's large build to suit lease for an unnamed frontier artificial intelligence laboratory. The lease is contracted and financed, while delivery remains scheduled in phases.
22Sourced facts4Source records5Open gaps
What the record establishes
- Contracted critical information technology load
- 191 MW[2]as of August 10th, 2026
- Initial lease contract revenue
- $9.1 billion[3]as of August 10th, 2026
- Potential contract revenue with both extensions
- $16.1 billion[3]as of August 10th, 2026
- Initial scheduled delivery
- 96 MW[3]
- Later scheduled delivery
- 95 MW[3]
- Interim financing facility
- $573 million[2]as of August 10th, 2026
- Initial lease term
- 20 years[3]
- Project design stated by Riot
- Build to suit Tier 3 data center[3]
- Initial delivery target
- December 2027[3]
- Full delivery target
- June 2028[3]
- Exact project company link in the financing filing
- RPI AUS01-0H DC LLC guarantees financing for the 191 MW Rockdale project[2]
- Developed Rockdale campus capacity
- 700 MW[4]
- Owner of record
- Riot Platforms, Inc.[1]registry read August 27th, 2026
- Occupant of record
- Riot Platforms, Inc.[1]registry read August 27th, 2026
- Operator of record
- Riot Platforms, Inc.[1]registry read August 27th, 2026
- Additional operator of record
- RPI Rockdale DC Holdings LLC[1]registry read August 27th, 2026
- Additional operator of record
- RPI DC Master LLC[1]registry read August 27th, 2026
- Additional operator of record
- Whinstone US, Inc[1]registry read August 27th, 2026
- Additional operator of record
- RPI Rockdale DC Campus LLC[1]registry read August 27th, 2026
- Additional operator of record
- RPI AUS01-0H DC LLC[1]registry read August 27th, 2026
- Additional operator of record
- Riot DC Logistics, LLC[1]registry read August 27th, 2026
- Certification effective
- June 1st, 2026[1]
What changes the reading
- The exact operator entity from this certification guarantees the financing for the large Rockdale project. That filing provides a stronger project bridge than the shared campus name alone.[1][2]
- Riot does not name the frontier laboratory in its securities filings. Outside attribution is not substituted for a filed customer identity.[3]
- The contract value includes rent across the lease term. It is not construction spending and the larger amount depends on optional extensions.[3]
- The developed campus figure covers mining and multiple data center leases. It is not assigned to this one certification and should not be added to the contracted customer load.[3][4]
- The delivery dates remain company targets. Financing and a signed lease do not establish that the new customer space is complete or energized.[2][3]
Still not public
- The frontier artificial intelligence laboratory has not been named.
- The physical boundary of this numbered certification is not public.
- Construction progress and delivered load are not public.
- Cooling design and expected water use are not public.
- The final long term financing structure is not public.
Source trail
- Data Center ListsTexas Comptroller of Public Accounts
- Riot Rockdale Interim Financing Current ReportUnited States Securities and Exchange Commission
- Riot Second Quarter Results and Rockdale UpdateUnited States Securities and Exchange Commission
- Riot CampusesRiot Platforms
The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.