SDC DFW VIII, L.P.

A Stream building in Wilmer with Google named as the certified occupant. State construction records show staged work inside the existing building and a much larger adjacent addition, each with its own cost, area and schedule.

13Sourced facts3Source records5Open gaps

What the record establishes

Owner of record
SDC DFW VIII, L.P.[1]registry read August 27th, 2026
Occupant of record
GOOGLE LLC[1]registry read August 27th, 2026
Operator of record
SDC DFW VIII, L.P.[1]registry read August 27th, 2026
Additional operator of record
Jones Lang La Salle Amercias, Inc.[1]registry read August 27th, 2026
Additional operator of record
Design, LLC[1]registry read August 27th, 2026
Address
300 South Sunrise Road, Wilmer, Dallas County[2]
New data halls in the first filing
2 buildings[2]
Capacity planned for each new hall
5 MW[2]
First filing area
60,000 sq ft[2]
First filing cost
$20 million[2]
Adjacent addition area
85,625 sq ft[3]
Adjacent addition filed cost
$167.3 million[3]
Adjacent addition completion target
December 2027[3]

What changes the reading

  • The first construction record describes work in an existing building. It says one hall was already in design and adds two more halls of equal planned capacity.[2]
  • The later filing describes an addition beside the existing data center. Its cost and area should not be added to the earlier scope as though both were delivered at the same time.[2][3]
  • The state registry spells one operator as Amercias. That spelling is preserved so a reader can match the public row rather than mistake a cleanup for a different entity.[1]
  • Google is established by the registry. The construction filings do not name the tenant and can't independently establish Google's occupied share.[1][2][3]

Still not public

  • Current delivered capacity and measured demand are not public.
  • Completion of the adjacent addition has not been confirmed.
  • Google's occupied share is not public.
  • Cooling design and measured water use are not public.
  • The reason for the three operator entities is not explained.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 27th, 2026.
  2. Stream Fig Accessibility ProjectTexas Department of Licensing and RegulationpermitRead August 27th, 2026.
  3. Stream Wilmer FIR Accessibility ProjectTexas Department of Licensing and RegulationpermitRead August 27th, 2026.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.