TX 301 Data Center

One of ten buildings the state certified on a single day, each under its own numbered Vantage entity, with Oracle as occupant on every one. Vantage has said its Shackelford County campus is ten data centers.

10Sourced facts3Source records4Open gaps

What the record establishes

Buildings certified together on this day
10 facilities[1]
Campus capacity Vantage announced
1.4 GW[2]
Campus area announced
1,200 acres[2]
Campus floor area announced
3,700,000 sq ft[2]
Announced investment
$25 billion[2]
Owner and operator of record
Vantage Data Centers TX301, LLC[1]as of October 8th, 2025
Occupant of record
Oracle America Cloud Services[1]registry read August 21st, 2026
Address on the construction filing
246 PR 1604 BLDG 1[3]
Building number in the filing
TX301[3]
Campus cooling
Liquid cooling for high density racks, per the developer[2]

What changes the reading

  • The count matches. Vantage announced a campus of ten data centers and the state certified ten numbered buildings on one day with the same occupant. That correspondence is not a statement from either party and it is not published here as one.[1][2]
  • Vantage holds other Texas certifications under lower numbers, filed separately and on a different date. Those are not part of this group of ten.[1]
  • The construction register arrives at the same campus size from the other side. Ten companies filed ten buildings separately. Their floor areas together come to very nearly the total Vantage announced before the first of them was filed, and neither register was built to check the other.[3][2]

Still not public

  • Vantage has not confirmed that these ten entities are the Shackelford campus.
  • Per building capacity and square footage are not public.
  • Energization dates per building are not public.
  • The certification carries no address, and the one here comes from the construction filing.

Source trail

  1. Data Center ListsTexas Comptroller of Public AccountsfilingRead August 21st, 2026.
  2. Vantage Data Centers Unveils Plans for Frontier, a Mega-campus in TexasVantage Data CenterscompanyRead August 21st, 2026.
  3. Texas Architectural Barriers Project SearchTexas Department of Licensing and RegulationfilingRead August 22nd, 2026.

What was filed to build it

Texas registers every large construction project with a second agency. These filings were made by a company this record already names.

$1.02 billion across 2 filings, 1,892,796 sq ft.

2026$950,000,000344,796 sq ftVantage DC Abilene - TX3 - Project FrontierAbilene
2026$74,000,0001,548,000 sq ftVantage DC Abilene - TX3 - Project FrontierAbilene

An estimated cost at filing is not a final cost, and a filing is not proof a building went up. How this register works.

The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.