Texas data centers Every registered facility.
TX 309 Data Center
One of three Frontier buildings built to the campus's larger floor plan. Its construction filing opens the second half of the campus schedule.
13Sourced facts4Source records4Open gaps
What the record establishes
- Data centers announced for the campus
- 10 buildings[3]as of August 19th, 2025
- Campus capacity announced
- 1.4 GW[3]as of August 19th, 2025
- Campus land announced
- 1,200 acres[3]as of August 19th, 2025
- Campus floor area announced
- 3,700,000 sq ft[3]as of August 19th, 2025
- Announced investment
- $25 billion[3]as of August 19th, 2025
- Workforce announced across construction and operations
- 5,000 workers[3]as of August 19th, 2025
- Owner and operator of record
- Vantage Data Centers TX309, LLC[1]as of October 8th, 2025
- Occupant of record
- Oracle America Cloud Services[1]registry read August 22nd, 2026
- Where the construction filing puts it
- Shackelford County, under an Abilene mailing address[2]
- Scheduled delivery of the first building on the campus
- Second half of 2026[3]as of August 19th, 2025
- Address on the construction filing
- 246 PR 1604 BLDG 9[2]
- Building number in the filing
- TX309[2]
- Campus cooling
- Liquid cooling on a closed loop chiller system[3]
What changes the reading
- Two campuses in this record answer to the name Abilene and they are not in the same county. This one sits in Shackelford County under an Abilene mailing address, which is ordinary for a rural site served by a distant post office. The Lancium Clean Campus, which opened the Stargate program, is inside Abilene in Taylor County. Both are occupied by the same Oracle entity, so a reader working from the city line alone would take them for one place.[1][2]
- The record moved after the announcement here. Vantage unveiled the campus in August and the Comptroller made all ten certifications effective on a single day that October. On the Lancium campus the order runs the other way.[1][3]
- The campus schedule divides cleanly in two, with five buildings filed to start before it and four after.[2]
- The construction register arrives at the same campus size from the other side. Ten companies filed ten buildings separately. Their floor areas together come to very nearly the total Vantage announced before the first of them was filed, and neither register was built to check the other.[2][3]
Still not public
- Vantage has not confirmed that these numbered entities are the announced campus.
- Per building capacity is not public.
- Energization dates per building are not public.
- The certification carries no address, and the one here comes from the construction filing.
Source trail
- Data Center ListsTexas Comptroller of Public Accounts
- Texas Architectural Barriers Project SearchTexas Department of Licensing and Regulation
- Vantage Data Centers Unveils Plans for Frontier, a Mega-campus in TexasVantage Data Centers
- Announcing The Stargate ProjectOpenAI
What was filed to build it
Texas registers every large construction project with a second agency. These filings were made by a company this record already names.
$1.16 billion across 1 filing, 398,117 sq ft.
2026$1.16 billion398,117 sq ftVantage DC Abilene - TX3 - Project FrontierAbilene
An estimated cost at filing is not a final cost, and a filing is not proof a building went up. How this register works.
The registry entry for this facility comes from the Texas Comptroller's certified list of data centers holding a sales tax exemption. Owner, occupant and operator are roles in that filing rather than descriptions of who runs the building.