Texas AI Docket

PUCT Project 58482, proposed new rule on Large Load Demand Management Service, open for comment

Power and the gridPublic Utility Commission of TexasERCOT regionComment window open

20days left to commentCloses September 4th

The Public Utility Commission of Texas has proposed a new rule governing demand management service for large electric loads, the category that covers data centers. The proposal for publication creates a new Section 25.521. Comments are open until September 4th, 2026. Individual Texans as well as utilities and data center operators have already filed.

How to take part

Anyone may file comments under control number 58482 through the PUCT Interchange filer at https://www.puc.texas.gov/industry/filings/Default.aspx. Individuals have already done so without counsel. The record contains filings from named members of the public alongside utility and data center filings. Comments must be in by the September 4th, 2026 deadline.

Where to do it

Where

No county is named for this item yet. It appears on no place page and lights nothing on the map.

Dates

DateWhatNote
2026-07-24orderedStaff memo and proposal for publication with a September 4th comment deadline
2026-07-30comment opensProposal for publication of new Section 25.521 filed
2026-09-04comment closesComment deadline in the Texas Register acknowledgement

The evidence

Every fact above rests on one of these. The words are the source's own.

Large Load Demand Management Service
PUCT Interchange, Filings for 58482, Case Style Primary source, official
PROPOSAL FOR PUBLICATION NEW §25.521
PUCT Interchange, control number 58482 item 30, filed by PUC OPDM, file stamp 7/30/2026 Primary source, official
Texas Register Acknowledgement of Receipt - Comment Deadline 09/04/2026
PUCT Interchange, control number 58482 item 31, filed by RULES & PROJECTS, file stamp 7/30/2026 Primary source, official
Project 58482 Commissioners Hearing Room 7-100 ( Open To Public )
PUCT calendar RSS, entry titled Public Comment Deadline - Friday, September 4, 2026 Primary source, official
Large Load Demand Services "Say No to incentives"
PUCT Interchange, Filings for 58482, item 32, party Jennifer Carrig, file stamp 8/3/2026 Primary source, official
CyrusOne, LP Comments in Response to Commission Staff's Qu
PUCT Interchange, Filings for 58482, item 25, party CyrusOne, LP, file stamp 4/8/2026 Primary source, official
33 filing(s).
PUCT Interchange, Filings for 58482 Primary source, official
Sec. 39.170. LARGE LOAD DEMAND MANAGEMENT SERVICE. (a) The commission shall require the independent organization certified under Section 39.151 for the ERCOT power region
Texas Utilities Code Sec. 39.170, added by SB 6 (89R) Primary source, official
develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition
Texas Utilities Code Sec. 39.170(b) Primary source, official

Last checked 2026-08-11