Texas AI Docket

When each one started

The earliest date on every entry's record. Answered here for 215 of the decisions on the record, from the same fields the decision page prints.

A Houston oil producer buys into an AI vendor and commits its Ward County operations to the vendor's system. When did it start?

The earliest date on its record is September 8th, 2026.

Open the decision.

A Sugar Land maker of AI data center optics says its United States expansion is waiting on electrical power. When did it start?

The earliest date on its record is November 5th, 2026.

Open the decision.

A Texas Senate committee set a hearing on how much water data center cooling uses and whether local water providers are told. When did it start?

The earliest date on its record is September 1st, 2026.

Open the decision.

A UT Austin dance and engineering team wins an award to build an AI model that learns from recorded human movement. When did it start?

The earliest date on its record is October 23rd, 2026.

Open the decision.

A data center developer tells its shareholders what the Batch Zero list did to five of its Texas projects, and one came back in a different class than it was filed in. When did it start?

The earliest date on its record is September 8th, 2026.

Open the decision.

A generative AI platform at UTMB reached the UT System Regents only on its third amendment, at $9,850,000, and now covers all seven health institutions. When did it start?

The earliest date on its record is December 1st, 2024.

Open the decision.

A machine scores the longer written answers on English STAAR first. When did it start?

The earliest date on its record is September 4th, 2026.

Open the decision.

A statewide poll finds most Texas voters oppose a data center in their own community for a second survey running. When did it start?

The earliest date on its record is August 13th, 2026.

Open the decision.

A three campus Texas trial tests whether a phone microphone held to the abdomen can count fetal movement by machine. When did it start?

The earliest date on its record is August 6th, 2026.

Open the decision.

Amarillo City Council authorizes a twenty year water supply agreement selling city water to Fermi America's Project Matador. When did it start?

The earliest date on its record is October 28th, 2025.

Open the decision.

Amazon and Wiwynn say they will expand the El Paso County plant that builds the racks going into AI data centers. When did it start?

The earliest date on its record is September 10th, 2026.

Open the decision.

Amazon selects Austin for a factory building the robotics systems used in its warehouses, and the mayor says no incentives were requested. When did it start?

The earliest date on its record is August 19th, 2026.

Open the decision.

An MD Anderson AI model reads where T cells gather in tumor tissue, and points at mucin as a wall that may keep them out. When did it start?

The earliest date on its record is October 13th, 2026.

Open the decision.

An MD Anderson and UT Medical Branch MRI model scored lower on patients it was not built on. When did it start?

The earliest date on its record is September 9th, 2026.

Open the decision.

Angelina County Commissioners Court adopts Resolution 010-26 asking the Legislature for authority over data centers. When did it start?

The earliest date on its record is July 14th, 2026.

Open the decision.

Archer County Commissioners Court unanimously denies a tax abatement for a Dynamo Ventures data center. When did it start?

The earliest date on its record is June 22nd, 2026.

Open the decision.

Asked for AI camera fire detections, Xcel counted cameras. When did it start?

The earliest date on its record is July 10th, 2025.

Open the decision.

Aurora tells shareholders its driverless trucks will run straight to customer sites in November, with its truck build about six weeks behind plan. When did it start?

The earliest date on its record is October 28th, 2026.

Open the decision.

Austin City Council adopted Ordinance 20260423-029 creating City Code Chapter 2-19 on surveillance technology. When did it start?

The earliest date on its record is February 5th, 2026.

Open the decision.

Austin City Council takes up a resolution to amend the land code for data centers. When did it start?

The earliest date on its record is August 5th, 2026.

Open the decision.

Austin City Council takes up a resolution to write data centers into a land development code that has no definition of one. When did it start?

The earliest date on its record is August 21st, 2026.

Open the decision.

Austin Community College drafts what it calls its first AI policy under a five rule framework and opens it to a town hall on October 12th. When did it start?

The earliest date on its record is October 9th, 2026.

Open the decision.

Austin bars its city manager from buying any park camera or drone that depends on artificial intelligence. When did it start?

The earliest date on its record is August 12th, 2026.

Open the decision.

Blanco-Pedernales Groundwater Conservation District signed a resolution asking the Legislature to clarify district authority over data centers. When did it start?

The earliest date on its record is April 16th, 2026.

Open the decision.

Brazoria County Commissioners Court adopted a resolution stating conditions it wants on data center development. When did it start?

The earliest date on its record is May 29th, 2026.

Open the decision.

Brazoria County Commissioners Court voted 5 to 0 to deny the reinvestment zone that four data center and power plant abatement applications depended on. When did it start?

The earliest date on its record is February 10th, 2026.

Open the decision.

Brazos County Commissioners Court assigns the RELLIS data center tax abatement to ThisWay Global after the original developer's bankruptcy. When did it start?

The earliest date on its record is April 29th, 2025.

Open the decision.

Brownsville takes up a temporary moratorium on data centers after staff tells the commission its code has no rules for them. When did it start?

The earliest date on its record is September 1st, 2026.

Open the decision.

Carson County Commissioners Court approves a phased tax abatement agreement with Fermi America for the Project Matador HyperGrid campus. When did it start?

The earliest date on its record is October 28th, 2025.

Open the decision.

Case managers beat Houston Methodist's discharge AI on the last day. When did it start?

The earliest date on its record is September 3rd, 2026.

Open the decision.

College Station City Council votes 4 to 2 to keep its Flock plate reader cameras on state and city roads. When did it start?

The earliest date on its record is September 24th, 2026.

Open the decision.

Comptroller bars state grant money from buying or renewing Flock cameras and other license plate readers. When did it start?

The earliest date on its record is October 13th, 2026.

Open the decision.

Conroe City Council fell short of the votes needed to put its Flock camera contract on the November ballot. When did it start?

The earliest date on its record is July 23rd, 2026.

Open the decision.

Corpus Christi City Council directed staff to write a zoning amendment prohibiting data centers in every zoning district and to prepare a moratorium process. When did it start?

The earliest date on its record is July 15th, 2026.

Open the decision.

DIR must run an AI regulatory sandbox letting state agencies test systems outside normal rules. When did it start?

The earliest date on its record is September 1st, 2025.

Open the decision.

Dallas Public Safety Committee sets a briefing on the police Flock plate reader program. When did it start?

The earliest date on its record is August 13th, 2026.

Open the decision.

Dallas issues its first code citations from the AI cameras on its brush trucks. When did it start?

The earliest date on its record is December 9th, 2025.

Open the decision.

Denton City Council takes up a data center moratorium resolution and a schedule of the public hearings it would require. When did it start?

The earliest date on its record is August 18th, 2026.

Open the decision.

ERCOT pauses energizing new large data centers and crypto mines until its audit is done. When did it start?

The earliest date on its record is September 14th, 2026.

Open the decision.

ERCOT starts sending the Batch Zero questionnaires, and a data center that does not answer comes off the list. When did it start?

The earliest date on its record is September 9th, 2026.

Open the decision.

ERCOT tells its board that AI training loads can fatigue grid generators and drafts a limit on how fast their power draw may swing. When did it start?

The earliest date on its record is August 26th, 2026.

Open the decision.

El Paso City Council adopted a letter asking Governor Abbott to clarify his data center directives. When did it start?

The earliest date on its record is August 11th, 2026.

Open the decision.

El Paso City Council adopts a Data Center Policy Framework requiring a Special Permit for hyperscale projects. When did it start?

The earliest date on its record is June 22nd, 2026.

Open the decision.

El Paso City Council amends its state legislative agenda to seek protection for residential ratepayers from data center utility costs. When did it start?

The earliest date on its record is June 16th, 2026.

Open the decision.

El Paso City Council orders Flock plate reader cameras off city property and bars new contracts without a further vote. When did it start?

The earliest date on its record is September 15th, 2026.

Open the decision.

El Paso passes two plate reader items as revised, filed to take city-sited readers down and bar new contracts. When did it start?

The earliest date on its record is September 15th, 2026.

Open the decision.

Energy Department funds a synthetic underground test pit at a Navasota drilling site to prove out mining automation. When did it start?

The earliest date on its record is September 9th, 2026.

Open the decision.

Energy Department research arm funds a Houston led team using AI to search for new magnet materials. When did it start?

The earliest date on its record is September 1st, 2026.

Open the decision.

ExxonMobil says three of its Permian rigs now drill with robotic pipe handling, and about half its Permian fleet will by 2028. When did it start?

The earliest date on its record is October 7th, 2026.

Open the decision.

FAA takes comment until October 11th on letting Zipline fly drone deliveries around the clock over five Texas metros. When did it start?

The earliest date on its record is September 11th, 2026.

Open the decision.

Federal comment window has closed on NRC reactor licensing and siting modernization. When did it start?

The earliest date on its record is July 16th, 2026.

Open the decision.

Federal comment window has closed on adding AI questions to the American Time Use Survey. When did it start?

The earliest date on its record is July 10th, 2026.

Open the decision.

Federal commodities regulator opens comment on trading derivatives whose underlying commodity is compute. When did it start?

The earliest date on its record is August 21st, 2026.

Open the decision.

Federal energy department opens comment on securing the grid and names AI as why demand grew, closing October 9th. When did it start?

The earliest date on its record is September 9th, 2026.

Open the decision.

Federal investigators opened a defect evaluation into a driverless system after crashes in Dallas and Austin. When did it start?

The earliest date on its record is May 6th, 2026.

Open the decision.

Federal regulators open an audit of how Tesla certified the Cybercab, on the day commercial deployment began in Austin. When did it start?

The earliest date on its record is September 3rd, 2026.

Open the decision.

Federal survey office asks whether the household internet survey should start measuring AI use, closing November 9th. When did it start?

The earliest date on its record is September 9th, 2026.

Open the decision.

Federal trucking regulators let driverless trucks warn traffic with a cab beacon instead of triangles. When did it start?

The earliest date on its record is October 7th, 2026.

Open the decision.

Fort Worth City Council unanimously began a 90 day data center moratorium and adopted grid filing requirements over one dissent. When did it start?

The earliest date on its record is August 11th, 2026.

Open the decision.

Four Texas campuses took roles in the Energy Department's AI for science program. When did it start?

The earliest date on its record is July 22nd, 2026.

Open the decision.

Frontera's queues close permanently on October 1st, 2026. When did it start?

The earliest date on its record is September 3rd, 2026.

Open the decision.

Google.org funds a UT Austin team to build AI surrogate models for testing fusion reactor designs. When did it start?

The earliest date on its record is October 16th, 2026.

Open the decision.

Governor Abbott directs the utility commission and ERCOT to audit every data center in the interconnection queue before any advances. When did it start?

The earliest date on its record is August 3rd, 2026.

Open the decision.

Governor directs the environmental agency to issue no data center permits until the grid audit is done. When did it start?

The earliest date on its record is September 21st, 2026.

Open the decision.

Governor directs the water board to enforce the state water use survey against data centers that did not return it. When did it start?

The earliest date on its record is September 14th, 2026.

Open the decision.

Governor orders state agencies to pause funding for Flock plate reader cameras. When did it start?

The earliest date on its record is August 28th, 2026.

Open the decision.

Grid operator asks the water board's questions and gives data centers until October 12th. When did it start?

The earliest date on its record is September 14th, 2026.

Open the decision.

Grid operator weighs a year's grace for data center cooling equipment on ride-through rules. When did it start?

The earliest date on its record is July 21st, 2026.

Open the decision.

Guadalupe County Commissioners Court unanimously approves ending the county's Flock Safety license plate reader contract. When did it start?

The earliest date on its record is August 4th, 2026.

Open the decision.

Harlingen Waterworks System board approves an effluent water supply agreement with RGV Property LLC for a proposed data center. When did it start?

The earliest date on its record is September 22nd, 2025.

Open the decision.

Harris County Commissioners Court renewed its Flock Group license plate reader and sound detection contract, then amended it to run county-wide. When did it start?

The earliest date on its record is May 18th, 2026.

Open the decision.

Hays County Commissioners Court adopted a 180-day emergency water review period for high water use developments and created a review board. When did it start?

The earliest date on its record is June 23rd, 2026.

Open the decision.

Hays County posts the sheriff's promise not to switch on AI report writing without coming back to the court. When did it start?

The earliest date on its record is September 1st, 2026.

Open the decision.

Hays County takes up a policy on how it governs AI in surveillance. When did it start?

The earliest date on its record is September 8th, 2026.

Open the decision.

Homeland Security tested facial biometric capture on pedestrians walking out of the country at the Progreso International Bridge. When did it start?

The earliest date on its record is October 1st, 2025.

Open the decision.

House Public Health held an interim hearing on artificial intelligence use in health care. When did it start?

The earliest date on its record is August 20th, 2026.

Open the decision.

House State Affairs held an interim hearing on data center development and the proposed 765 kV transmission lines. When did it start?

The earliest date on its record is August 19th, 2026.

Open the decision.

Houston ISD carried an artificial intelligence board policy to a second reading. When did it start?

The earliest date on its record is March 20th, 2026.

Open the decision.

Houston Methodist put an imaging AI in front of its radiologists and says out loud that it is imperfect. When did it start?

The earliest date on its record is June 29th, 2026.

Open the decision.

Houston Methodist ties camera AI in 15 cardiothoracic surgery rooms to about 25 more cases a month, and says it can't prove the cameras caused it. When did it start?

The earliest date on its record is June 27th, 2026.

Open the decision.

Houston academic physician group moves from two ambient AI pilots toward one unified documentation platform. When did it start?

The earliest date on its record is September 9th, 2026.

Open the decision.

Houston-Galveston Area Council put AI consulting services on its HGACBuy purchasing catalog under contract AI05-26. When did it start?

The earliest date on its record is May 1st, 2026.

Open the decision.

Judges back El Paso Electric's gas plant for Meta only if other customers don't pay. When did it start?

The earliest date on its record is December 8th, 2025.

Open the decision.

Justice Department takes comment on a judgment barring a Frisco apartment manager from rent software fed by rivals' data. When did it start?

The earliest date on its record is September 4th, 2026.

Open the decision.

Killeen Planning and Zoning Commission voted against a conditional use permit for a $30 million ONMINE data center. When did it start?

The earliest date on its record is April 27th, 2026.

Open the decision.

Kodiak and Charger USA start hauling freight between Dallas and Laredo on autonomous trucks with a safety driver behind the wheel. When did it start?

The earliest date on its record is September 8th, 2026.

Open the decision.

Kodiak names Interstate 45 from Dallas to Houston as its first driverless truck lane, and says it closes its safety case before the driver comes out. When did it start?

The earliest date on its record is September 25th, 2026.

Open the decision.

Laredo City Council declined a data center moratorium, and its direction to write permanent rules has reached three agendas with no recorded action. When did it start?

The earliest date on its record is July 27th, 2026.

Open the decision.

League City City Council ordered a November 3rd special election on whether police may keep using automated license plate reader cameras. When did it start?

The earliest date on its record is August 5th, 2026.

Open the decision.

Leander stops paying for its plate reader contract and says the police department is no longer using the cameras or the data. When did it start?

The earliest date on its record is September 3rd, 2026.

Open the decision.

Lockheed Martin brings Hadrian's 24 machine automated machining cell into its Grand Prairie missile parts plant. When did it start?

The earliest date on its record is October 14th, 2026.

Open the decision.

Lubbock County Commissioners Court passes a non binding disclosure resolution on large scale industrial development, four to one. When did it start?

The earliest date on its record is August 10th, 2026.

Open the decision.

Lubbock starts the procedure for a 90 day data center moratorium after the 18 month petition fails. When did it start?

The earliest date on its record is September 8th, 2026.

Open the decision.

Memorial Hermann clinicians send Houston patients an AI drafted explanation of their own test results. When did it start?

The earliest date on its record is September 8th, 2026.

Open the decision.

NSF awarded Prairie View A and M a grant to let AI split up the grid optimization problem across processor cores. When did it start?

The earliest date on its record is August 11th, 2026.

Open the decision.

NSF awarded UT Austin a grant to replace hand written robot safety rules with a model trained on demonstrated safe behavior. When did it start?

The earliest date on its record is August 13th, 2026.

Open the decision.

NSF funds a Rice laboratory where a model designs the experiment and a robot runs it, bookable from anywhere. When did it start?

The earliest date on its record is August 1st, 2026.

Open the decision.

National Science Foundation awards Rice University a cooperative agreement for a self driving laboratory that designs its own semiconductor experiments. When did it start?

The earliest date on its record is July 21st, 2026.

Open the decision.

National Science Foundation awards Texas A and M a national user facility where robots and artificial intelligence design and test new metal alloys. When did it start?

The earliest date on its record is July 31st, 2026.

Open the decision.

National Science Foundation backs a Texas A&M tool that screens whether an alloy can exist before anyone makes it. When did it start?

The earliest date on its record is September 4th, 2026.

Open the decision.

National Science Foundation funds Rice to let AI propose numerical algorithms only where a proof checker certifies them. When did it start?

The earliest date on its record is August 17th, 2026.

Open the decision.

National Science Foundation funds Sagebrush, an AI inference platform for researchers nationwide, hosted at UT Austin's supercomputing center. When did it start?

The earliest date on its record is July 20th, 2026.

Open the decision.

National Science Foundation funds UT San Antonio and Texas A&M to adapt large language models on machines that can't afford to run them. When did it start?

The earliest date on its record is August 14th, 2026.

Open the decision.

National Science Foundation funds a five year human and robot co-adaptation center at UT Austin. When did it start?

The earliest date on its record is August 25th, 2026.

Open the decision.

National Science Foundation funds an open access robot run alloy laboratory at Texas A&M that outside researchers may book. When did it start?

The earliest date on its record is July 31st, 2026.

Open the decision.

National Science Foundation makes Texas Southern University one of five regional nodes in an HBCU network for AI and quantum science. When did it start?

The earliest date on its record is September 17th, 2026.

Open the decision.

National Science Foundation names UT El Paso in the first round of CyberAICorps Scholarship for Service awards. When did it start?

The earliest date on its record is July 28th, 2026.

Open the decision.

National Science Foundation puts UT Austin's supercomputing center in an operating role for the national AI research resource. When did it start?

The earliest date on its record is September 1st, 2026.

Open the decision.

PUCT Docket 59029, Oncor application for a second 765 kV line across ten west Texas counties. When did it start?

The earliest date on its record is August 21st, 2026.

Open the decision.

PUCT Docket 59315, Oncor application for a 765 kV transmission line across 22 counties. When did it start?

The earliest date on its record is February 2nd, 2026.

Open the decision.

PUCT Project 58000, rulemaking to update ERCOT transmission cost recovery, comment deadline reached. When did it start?

The earliest date on its record is April 23rd, 2025.

Open the decision.

PUCT Project 58482, proposed new rule on Large Load Demand Management Service, comment window now shut. When did it start?

The earliest date on its record is July 24th, 2026.

Open the decision.

PUCT adopts the SB 6 large load interconnection rule, requires $50,000 per megawatt of security and drops the interconnection fee. When did it start?

The earliest date on its record is September 18th, 2026.

Open the decision.

PUCT open meeting calendar published as a live feed through mid 2027. When did it start?

The earliest date on its record is August 20th, 2026.

Open the decision.

PUCT told an Armstrong County AI data center to shed its whole load, then left those conditions in place. When did it start?

The earliest date on its record is January 9th, 2026.

Open the decision.

PUCT wildfire plan blueprint lists cameras suggested, not required. When did it start?

The earliest date on its record is December 4th, 2025.

Open the decision.

PUCT's first five year review of the ERCOT system-wide offer caps closed to comment on September 17th. When did it start?

The earliest date on its record is March 23rd, 2026.

Open the decision.

Pecos-Barstow-Toyah ISD's JETI agreement for the Energy Forge One power plant is executed and posted. When did it start?

The earliest date on its record is November 10th, 2025.

Open the decision.

Permian Resources tells investors it now runs an AI system that watches its artificial lift. When did it start?

The earliest date on its record is November 4th, 2026.

Open the decision.

Pflugerville orders a November election on charter amendments, one of them a section on the city's use of artificial intelligence. When did it start?

The earliest date on its record is August 11th, 2026.

Open the decision.

Pflugerville's City Council adopts SAFE standards for how the city uses technology, with facial recognition covered. When did it start?

The earliest date on its record is August 11th, 2026.

Open the decision.

Plano's City Council takes up to $390,000 for ChatGPT Enterprise and the Darwin AI platform. When did it start?

The earliest date on its record is October 12th, 2026.

Open the decision.

Reeves County Emergency Services District No. 2 takes up a Chapter 312 abatement for a gas plant built to run data centers. When did it start?

The earliest date on its record is November 24th, 2025.

Open the decision.

Rice University sets out to hire 40 more AI faculty, for 75 this decade, and to take lab space at The Arc in Houston's Ion District. When did it start?

The earliest date on its record is October 13th, 2026.

Open the decision.

Rice University sets out to hire 75 faculty working on AI and plans a research building for it in Houston's Ion District. When did it start?

The earliest date on its record is October 13th, 2026.

Open the decision.

Richardson ISD drafts a legislative ask that puts classroom AI guidance first. When did it start?

The earliest date on its record is September 18th, 2026.

Open the decision.

Round Rock says its zoning does not cover drone delivery hubs as Zipline starts flying from one outside city limits. When did it start?

The earliest date on its record is October 9th, 2026.

Open the decision.

San Angelo City Council caps data center cooling water by ordinance. When did it start?

The earliest date on its record is May 19th, 2026.

Open the decision.

San Angelo sets reporting rules for data center coolant discharged into the city sewer. When did it start?

The earliest date on its record is May 19th, 2026.

Open the decision.

San Angelo writes data centers into its zoning code and makes them a conditional use only. When did it start?

The earliest date on its record is April 20th, 2026.

Open the decision.

San Antonio council requires its own approval for every new data center. When did it start?

The earliest date on its record is October 29th, 2026.

Open the decision.

San Antonio counts loose dogs in 32 study areas with phone cameras and object detection software. When did it start?

The earliest date on its record is October 20th, 2026.

Open the decision.

San Antonio takes two data center zoning proposals to a public hearing on October 20th and a council vote on October 29th. When did it start?

The earliest date on its record is October 20th, 2026.

Open the decision.

San Marcos City Council voted 4 to 3 to define data centers in its land development code and make them ineligible citywide. When did it start?

The earliest date on its record is June 16th, 2026.

Open the decision.

Saronic breaks ground at the Port of Brownsville on Port Alpha, a shipyard built to make autonomous and crewed ships, on a Cameron County abatement. When did it start?

The earliest date on its record is September 30th, 2026.

Open the decision.

Science foundation funds a Texas A&M engineering station to build AI digital twins of small water systems. When did it start?

The earliest date on its record is September 9th, 2026.

Open the decision.

Senate Economic Development holds its reset hearing on AI and the Texas workforce on September 22nd. When did it start?

The earliest date on its record is September 3rd, 2026.

Open the decision.

Senate Transportation held its August 25th hearing on how driverless vehicles are being deployed under SB 2807. When did it start?

The earliest date on its record is August 25th, 2026.

Open the decision.

Senate Water, Agriculture and Rural Affairs has held both sittings on data center cooling water and published no recommendation. When did it start?

The earliest date on its record is September 1st, 2026.

Open the decision.

Soluna and Applied Digital agree to build an AI data center beside the Briscoe Wind Farm, if Briscoe County grants a tax abatement. When did it start?

The earliest date on its record is October 21st, 2026.

Open the decision.

SpaceX asks Starbase for a tax abatement on a $24 billion gas-fired power plant and super-compute facility beside Brownsville, with a hearing December 9th. When did it start?

The earliest date on its record is December 9th, 2026.

Open the decision.

SpaceX will build the Terafab semiconductor plant in Grimes County on a state grant and two school district agreements. When did it start?

The earliest date on its record is August 6th, 2026.

Open the decision.

State education staff helped Alpha School's AI platform into pilots in Houston, Aldine and Fort Davis. When did it start?

The earliest date on its record is June 27th, 2025.

Open the decision.

State technology agency publishes how it is implementing the four AI laws of the 89th Legislature. When did it start?

The earliest date on its record is August 14th, 2026.

Open the decision.

Statute requires state agencies and local governments to post standardized notice of AI systems. When did it start?

The earliest date on its record is September 1st, 2025.

Open the decision.

TACC retires Frontera after more than eight million jobs, and a UT Southwestern simulation that needed 64 of its CPU nodes runs nearly as fast on eight Vista GPU nodes. When did it start?

The earliest date on its record is October 29th, 2026.

Open the decision.

TCEQ canceled the Carson County public meeting on Fermi Equipment Holdco's new air permits and says it will be rescheduled. When did it start?

The earliest date on its record is August 12th, 2026.

Open the decision.

TCEQ canceled the San Antonio notice and comment hearing on Vantage Data Centers TX11's air permit O4791. When did it start?

The earliest date on its record is August 11th, 2026.

Open the decision.

TCEQ has four data center air permit applications posted with published public notices, including Crusoe's two Texas campuses. When did it start?

The earliest date on its record is August 14th, 2026.

Open the decision.

TCEQ issues preliminary decision and opens comment on Crusoe's gas power plant at the Abilene data center campus. When did it start?

The earliest date on its record is November 7th, 2025.

Open the decision.

TRAIGA in force as Business and Commerce Code Chapter 552, enforceable only by the Attorney General. When did it start?

The earliest date on its record is June 22nd, 2025.

Open the decision.

TRAIGA preempts city and county regulation of artificial intelligence. When did it start?

The earliest date on its record is January 1st, 2026.

Open the decision.

Tarrant Regional Water District says it has signed no water supply contract for a data center and that the Cedar Creek request was withdrawn. When did it start?

The earliest date on its record is June 23rd, 2026.

Open the decision.

Taylor City Council approves an agreement to annex a 664 acre data center campus under written water, setback and noise terms. When did it start?

The earliest date on its record is October 2nd, 2026.

Open the decision.

Taylor City Council unanimously approved the amended Compal tax abatement agreement. When did it start?

The earliest date on its record is August 13th, 2026.

Open the decision.

Temple Planning and Zoning Commission takes up a Unified Development Code amendment that would require a Conditional Use Permit for every future data center. When did it start?

The earliest date on its record is August 17th, 2026.

Open the decision.

Tesla's own capacity table puts the Cybercab in production in Texas and lists the Texas Optimus robot line as still under construction. When did it start?

The earliest date on its record is October 21st, 2026.

Open the decision.

Texas 2036 finds AI in most Texas classrooms and a written AI policy in few districts, and asks the state for guidance. When did it start?

The earliest date on its record is November 10th, 2026.

Open the decision.

Texas A&M builds a language model that sorts disaster posts for emergency managers, and it has not yet been used in a live disaster. When did it start?

The earliest date on its record is November 6th, 2026.

Open the decision.

Texas A&M researchers find language models trained on junk social media posts start skipping reasoning steps, and better data doesn't fully fix them. When did it start?

The earliest date on its record is October 19th, 2026.

Open the decision.

Texas A&M scientists use AlphaFold to screen every pairing of human mitochondrial proteins and publish the likely partners free. When did it start?

The earliest date on its record is August 25th, 2026.

Open the decision.

Texas A&M takes a $2 million WoodNext Foundation grant to build the Aggie AI Foundry, where AI and robots would design and test new metal alloys. When did it start?

The earliest date on its record is October 22nd, 2026.

Open the decision.

Texas A&M tells its campus to run AI through a university portal rather than a public chatbot. When did it start?

The earliest date on its record is August 31st, 2026.

Open the decision.

Texas Children's and Baylor researchers name a likely genetic cause of a rare disorder after an AI tool flagged the gene. When did it start?

The earliest date on its record is September 28th, 2026.

Open the decision.

Texas Children's and UT Southwestern radiologists publish that imaging AI has largely skipped children. When did it start?

The earliest date on its record is September 9th, 2026.

Open the decision.

Texas Government Code Chapter 2054 carries three conflicting Subchapter S's on AI, with duplicated section numbers. When did it start?

The earliest date on its record is September 1st, 2025.

Open the decision.

Texas State University moves an AI pavement inspection method toward statewide highway use. When did it start?

The earliest date on its record is August 24th, 2026.

Open the decision.

Texas Water Development Board denied a petition to give data centers their own water demand category and adopted the 2027 State Water Plan the same day. When did it start?

The earliest date on its record is July 22nd, 2026.

Open the decision.

Texas requires AI training for state and local government employees, and this is the first annual cycle. When did it start?

The earliest date on its record is September 1st, 2025.

Open the decision.

Texas requires a state authorization to run driverless vehicles commercially, with no fee, no expiry and no crash history asked. When did it start?

The earliest date on its record is February 27th, 2026.

Open the decision.

The Army funds a Rice research center on antenna arrays that carries AI as one of six disciplines. When did it start?

The earliest date on its record is August 4th, 2026.

Open the decision.

The Fifteenth Court of Appeals leaves Bot Auto free to keep building driverless trucks while TuSimple's successor sues it over trade secrets. When did it start?

The earliest date on its record is September 15th, 2026.

Open the decision.

The Hays County Clerk asks the commissioners court to buy AI that writes the county's official minutes. When did it start?

The earliest date on its record is September 15th, 2026.

Open the decision.

The House committee on government efficiency is charged with studying whether the state should use artificial intelligence to find fraud in its own spending. When did it start?

The earliest date on its record is August 19th, 2026.

Open the decision.

The National Science Foundation funds a Texas A&M project to build AI digital twins of small and mid-sized water systems. When did it start?

The earliest date on its record is September 9th, 2026.

Open the decision.

The National Science Foundation funds a UT Austin center to put assistive robots into occupied homes, workplaces and care facilities. When did it start?

The earliest date on its record is August 25th, 2026.

Open the decision.

The National Science Foundation puts Texas Southern University in charge of one of five regional nodes in a new HBCU network for AI and quantum science. When did it start?

The earliest date on its record is September 17th, 2026.

Open the decision.

The National Science Foundation puts the national AI research resource into standing operations, co-run from Austin. When did it start?

The earliest date on its record is September 1st, 2026.

Open the decision.

The Supreme Court of Texas heard argument on whether a deposition transcript made with AI can stand without a certified court reporter. When did it start?

The earliest date on its record is May 29th, 2025.

Open the decision.

The Texas A&M System's shared AI supercomputer enters the world list at number 66. When did it start?

The earliest date on its record is January 1st, 2025.

Open the decision.

The University of North Texas takes a twenty million dollar gift and names a college of artificial intelligence after the donors. When did it start?

The earliest date on its record is September 8th, 2026.

Open the decision.

The University of Texas at Austin requires every course syllabus to state its AI policy. When did it start?

The earliest date on its record is August 24th, 2026.

Open the decision.

The board takes a required high school money course to final adoption, and the text it published names AI tools in three of its chapters. When did it start?

The earliest date on its record is September 4th, 2026.

Open the decision.

The grid operator sends every conditionally classified large load a questionnaire, with a notarized attestation and ten business days to answer. When did it start?

The earliest date on its record is September 3rd, 2026.

Open the decision.

The grid operator sets an October 6th workshop on how it would curtail a large load under Senate Bill 6. When did it start?

The earliest date on its record is September 2nd, 2026.

Open the decision.

The grid operator tells providers which large loads it has provisionally placed in Batch Zero, and every placement carries a condition. When did it start?

The earliest date on its record is September 3rd, 2026.

Open the decision.

The state's chip fund gives Texas Tech over $19 million for an AI computing cluster in Lubbock that is meant to speed up semiconductor research. When did it start?

The earliest date on its record is November 13th, 2026.

Open the decision.

The utility commission sues the Attorney General to keep the county and water planning area of each surveyed data center from release. When did it start?

The earliest date on its record is October 5th, 2026.

Open the decision.

Tom Green County Commissioners Court declines a Precinct 4 moratorium on data centers and large energy projects. When did it start?

The earliest date on its record is June 2nd, 2026.

Open the decision.

Two Texas House committees take up data centers and AI in health care on August 19th and August 20th. When did it start?

The earliest date on its record is August 19th, 2026.

Open the decision.

TxDOT starts Project Nexus, a three year state test of next generation aircraft whose first flights carry no passengers. When did it start?

The earliest date on its record is September 10th, 2026.

Open the decision.

USDA's Kerrville laboratory builds AI models that pick where, when and how many sterile flies to release against New World screwworm. When did it start?

The earliest date on its record is October 12th, 2026.

Open the decision.

UT Arlington develops a federally funded AI tutor and tests related technology with Fort Worth police. When did it start?

The earliest date on its record is September 10th, 2026.

Open the decision.

UT Arlington replaces its business analytics degrees with artificial intelligence degrees. When did it start?

The earliest date on its record is September 14th, 2026.

Open the decision.

UT Austin funds four fusion seed grants and says in its own release that the AI method offers limited guarantees. When did it start?

The earliest date on its record is August 31st, 2026.

Open the decision.

UT Austin puts a computer science and AI course in the core every undergraduate takes. When did it start?

The earliest date on its record is August 13th, 2026.

Open the decision.

UT REAL Health AI signs a systemwide agreement letting UT health institutions use Abridge's ambient note taking. When did it start?

The earliest date on its record is October 8th, 2026.

Open the decision.

UT San Antonio builds a free training platform where students learn to find the security flaws in code an AI wrote. When did it start?

The earliest date on its record is September 23rd, 2026.

Open the decision.

UT San Antonio builds a solar powered flood sensor that runs its model on the chip rather than in the cloud. When did it start?

The earliest date on its record is September 28th, 2026.

Open the decision.

UT San Antonio builds a solar powered flood sensor that runs its model on the device instead of a server. When did it start?

The earliest date on its record is September 28th, 2026.

Open the decision.

UT Southwestern finds AI triage models moved some emergency patients who later got worse down the line after one stigmatizing detail was added. When did it start?

The earliest date on its record is October 20th, 2026.

Open the decision.

UT System Board of Regents approved a School of Computing at UT Austin uniting computer science, information, statistics and data sciences. When did it start?

The earliest date on its record is February 19th, 2026.

Open the decision.

UT System Board of Regents approves $25 million to finish San Pedro II for UTSA's College of AI, Cyber and Computing. When did it start?

The earliest date on its record is May 20th, 2026.

Open the decision.

UT System Regents put the first billion dollars of the UT Dell Medical Center into the capital program. When did it start?

The earliest date on its record is August 12th, 2026.

Open the decision.

UTEP and El Paso Water test whether a NASA backed AI model can map flooded streets from satellite images after a storm. When did it start?

The earliest date on its record is October 8th, 2026.

Open the decision.

UTMB moved its Epic health record into Microsoft's cloud and named advanced technologies as the reason. When did it start?

The earliest date on its record is August 13th, 2026.

Open the decision.

UTMB puts OpenEvidence's AI answers inside its health record and says more than half of its clinicians use it. When did it start?

The earliest date on its record is September 22nd, 2026.

Open the decision.

Utilities Code limits how the PUCT may direct ERCOT, and bars verbal directives. When did it start?

The earliest date on its record is June 8th, 2021.

Open the decision.

Utility commission approves a 765 kilovolt line from Somervell County to Howard County. When did it start?

The earliest date on its record is February 19th, 2026.

Open the decision.

Volvo and Waabi start hauling a customer's freight between Dallas and Houston on autonomous trucks, with an observer in the driver's seat. When did it start?

The earliest date on its record is October 5th, 2026.

Open the decision.

Waymo opens its San Antonio robotaxis to anyone with the app, the airport included, while its flood recall remedy is still listed as under development. When did it start?

The earliest date on its record is October 14th, 2026.

Open the decision.

West Texas A&M wins a USDA grant to build a research feedlot near Canyon that will test feeding, health and handling with AI powered methods. When did it start?

The earliest date on its record is October 7th, 2026.

Open the decision.

Wichita Falls Planning and Zoning Commission approves a conditional use permit for a DataNovaX data center on Airport Drive. When did it start?

The earliest date on its record is August 13th, 2026.

Open the decision.

Williamson County Commissioners Court granted Compal USA Technology a Chapter 312 abatement for a Georgetown server service center. When did it start?

The earliest date on its record is December 9th, 2025.

Open the decision.

Young County Commissioners Court receives the Project Saltworks tax abatement application and ratifies a developer funded escrow for consultants. When did it start?

The earliest date on its record is August 10th, 2026.

Open the decision.