Young County Commissioners Court receives the Project Saltworks tax abatement application and ratifies a developer funded escrow for consultants
Young County Commissioners Court formally received a tax abatement application from Headwaters Site Development for the Project Saltworks data center campus at the courthouse in Graham on August 10th, 2026. That agenda item required no vote, and County Judge Win Graham said he would hand the application to the county clerk so it becomes a public document. Commissioners did vote to ratify a separate escrow agreement under which the developer puts up 250,000 dollars to pay for the county's outside consultants while it evaluates the project. Residents used public comment to ask the court to slow down and wait for the Legislature before granting any incentive. Commissioner Alan Craig said the application contained no specifics and that the court would know more when it convenes again on August 17th.
How to take part
The Commissioners Court meets in open session at the Young County Courthouse in Graham and takes public comment before acting. Residents used that period at the August 10th meeting to press commissioners on roads, water, emergency services and environmental studies. The abatement application is now a public document held by the county clerk.
Where
1 county. In Young, which is in no metropolitan or micropolitan area.
Dates
| Date | What | Note |
|---|---|---|
| 2026-08-10 | filed | County received Headwaters Site Development's tax abatement application for Project Saltworks and voted 5 to 0 to ratify the escrow agreement |
| 2026-08-17 | hearing | Commissioners Court reconvenes to begin considering the abatement request, per Commissioner Alan Craig |
The evidence
Every fact above rests on one of these. The words are the source's own.
GRAHAM — Young County Commissioners took another step toward negotiations over the proposed Project Saltworks data center campus on Aug. 10, formally receiving a tax abatement application from the project's developer while opponents again urged county officials to slow down or reject incentives altogether.County Votes on Data Center Abatement | Olney Enterprise Journalism
Commissioners did vote 5-0 to ratify a separate escrow agreement under which Headwaters will provide $250,000 to cover the county's costs for consultants as it evaluates the project.County Votes on Data Center Abatement | Olney Enterprise Journalism
The receipt of the abatement application does not mean commissioners have approved a tax abatement for Project Saltworks.County Votes on Data Center Abatement | Olney Enterprise Journalism
"There's no meat in the sandwich right now. That will likely change starting next Monday."County Votes on Data Center Abatement | Olney Enterprise Journalism