TCEQ has four data center air permit applications posted with published public notices, including Crusoe's two Texas campuses

Land, water and permittingTexas Commission on Environmental Quality, Air Permits DivisionStatewideWrite to the decider

TCEQ's pending new source review page lists air permit applications whose notices are open to the public. Four of them are data centers. Aligned Data Centers REIT LLC is listed at ADC Plano and Amazon.com Services LLC at TXZ5. Crusoe Energy Systems LLC appears twice, at the Longhorn Data Center and at the Goodnight Data Center. Each row carries a plain language summary in English and Spanish and a notice of receipt of application. Several also carry a notice of application and preliminary decision, which is the document that opens the formal comment window. Crusoe's Longhorn permits include prevention of significant deterioration and greenhouse gas PSD authorizations. That is the permit family covering on site power generation rather than a few backup engines.

How to take part

Each listed application links a plain language summary and the published notices. Comments go to the TCEQ Office of the Chief Clerk at P.O. Box 13087 in Austin. Use mail code MC-105 and postal code 78711-3087. Comments may also be filed through the eComment system. A person who may be affected by emissions can request a contested case hearing.

Where to do it

Where

Statewide. This decision applies across Texas rather than to a named county.

Timeline

  1. comment opens

    date this listing was fetched and the four data center applications were shown with published notices

  2. Today

How this decision moved

One dated line per check, oldest first. A line that says nothing changed means somebody looked and it had not.

  1. 2026-08-19

    Checked and unchanged. The pending notice list still carries all four data center applications, Aligned at ADC Plano, Amazon at TXZ5 and Crusoe at both Longhorn and Goodnight.

  2. 2026-08-22

    Checked and unchanged. The pending notice list still carries all four data center applications. They are Aligned at ADC Plano, Amazon at TXZ5 and Crusoe at both the Longhorn and Goodnight campuses, each with its published notices.

  3. 2026-08-26

    Checked and unchanged. The four applications are still posted with published notices and the agency still requires an applicant to publish notice and a plain language summary.

  4. 2026-08-29

    Checked and unchanged. The pending applications list still carries the four data center air permits with their published notices. The requirement that an applicant publish notice and provide a plain language summary is unchanged.

  5. 2026-09-02

    The applications are still posted with published public notices and none has been withdrawn.

  6. 2026-09-05

    The agency's pending permit list still carries the data center applications with published notice. None has been withdrawn.

  7. 2026-09-08

    The state environmental agency still posts the same four data center air permit applications with public notices, and Crusoe's two Texas campuses are still among them. None has moved to a decision.

  8. 2026-09-09

    The four data center air permit applications are still posted as pending with published public notice.

  9. 2026-09-12

    The four data center air permit applications are still posted as pending with published public notice, and the agency's plain language summary requirement still governs them.

  10. 2026-09-13

    The data center air permit applications are still posted as pending with published notice, and none has moved off that list.

  11. 2026-09-16

    The agency still has four data center air permit applications posted with published notices. None has moved to a decision.

  12. 2026-09-19

    The applications are still posted as pending with their public notices published, which is the point at which a neighbor can still ask for a contested hearing.

  13. 2026-09-24

    The applications are still posted as pending with their public notices, which is the stage at which a neighbor can still ask for a contested hearing.

  14. 2026-09-27

    The pending permit list still carries the data center applications with their public notices, so the window to ask for a contested hearing is still the live one.

  15. 2026-09-30

    The agency's pending permit list still carries the data center applications with their published notices.

The evidence

Every fact above rests on one of these. The words are the source's own.

Air permit applicants are required to publish notice and provide plain language summaries in accordance with 30 TAC Chapter 39 Subchapter H. These documents are available in English and may be required in alternative languages.
Summaries and Public Notices for Pending New Source Review Permit Applications - TCEQ Primary source, official · tceq.texas.gov

Questions about this decision

Answered from the record itself. Every answer is assembled from stored fields, so an answer the record has no basis for is left out rather than guessed.

What is this decision?

TCEQ's pending new source review page lists air permit applications whose notices are open to the public. Four of them are data centers. Aligned Data Centers REIT LLC is listed at ADC Plano and Amazon.com Services LLC at TXZ5. Crusoe Energy Systems LLC appears twice, at the Longhorn Data Center and at the Goodnight Data Center. Each row carries a plain language summary in English and Spanish and a notice of receipt of application. Several also carry a notice of application and preliminary decision, which is the document that opens the formal comment window. Crusoe's Longhorn permits include prevention of significant deterioration and greenhouse gas PSD authorizations. That is the permit family covering on site power generation rather than a few backup engines.

Who decides it?

Texas Commission on Environmental Quality, Air Permits Division decides. The record names the deciding body for every entry it carries.

Can the public take part?

Each listed application links a plain language summary and the published notices. Comments go to the TCEQ Office of the Chief Clerk at P.O. Box 13087 in Austin. Use mail code MC-105 and postal code 78711-3087. Comments may also be filed through the eComment system. A person who may be affected by emissions can request a contested case hearing. No dated public window is on the record. The deciding body is named and reachable.

Where in Texas does it apply?

It is a statewide body's action and it governs the ERCOT region rather than every county.

Has it been decided?

It is pending. No final decision is on the record.

What happens next?

No future date is on the record. The last dated step on it was comment opens on August 14th.

When did it start?

The earliest date on its record is August 14th, 2026.

What kind of decision is it?

It is filed under land, water and permitting.

What sources back it?

One source backs it. It is primary.

Is it on the ERCOT grid?

Yes. It sits inside the ERCOT interconnection.

When was it last checked?

Every fact on it was last verified against its source on September 30th, 2026.

Cite this

Texas AI Docket, TCEQ has four data center air permit applications posted with published public notices, including Crusoe's two Texas campuses. Tracked since August 14th, 2026. Last verified September 30th, 2026. https://texasaidocket.com/item/tx-2026-0063/. Reuse permitted under CC BY 4.0 with attribution. The same entry is in the docket JSON as item tx-2026-0063.

Beat

Filed under Land, water and permitting, with every other decision on that beat.

Last checked 2026-09-30