Taylor City Council approves an agreement to annex a 664 acre data center campus under written water, setback and noise terms
The City of Taylor has a proposed development agreement with Big Watt Digital and PowerHouse Data Centers for Taylor Technology Campus. The 664 acre site was known as Project Mustang and includes data centers and on site power generation. The City Council approved the agreement 5 to 0 at its meeting on October 8th, 2026. The developers had withdrawn their annexation and zoning application with the city. The city's notice says the land would otherwise stay in unincorporated Williamson County, which has no zoning authority. Under the agreement the site is annexed and held to written terms. Cooling is a closed loop filled with reclaimed water, and potable water is barred from cooling except in circumstances the agreement names. Buildings sit at least 300 feet from the north, east and west lines. Data centers, generation and batteries sit at least 700 feet from the south line. Noise may not exceed the greater of 65 dBA or the level measured before construction. The developers commit $28.2 million for community investments and nonprofit support and ask for no tax abatement. Air quality stays with TCEQ.
How to take part
The council approved the agreement on October 8th, 2026. The city's website carries archived meeting video.
Where
1 county. In Austin-Round Rock-San Marcos.
Timeline
- filed
The city posts its notice of the proposed development agreement
- hearing
City Council meeting, vote on the development agreement
- decided
The City Council approves the development agreement 5 to 0
- Today
How this decision moved
One dated line per check, oldest first. A line that says nothing changed means somebody looked and it had not.
- 2026-10-06
Admitted on the city's own notice. The council has not voted yet. The agreement's full text was not found posted beside the notice.
- 2026-10-07
The council has not voted yet. The city's page still sets out the proposed terms beside what applies without them.
- 2026-10-08
Taylor's council has not voted yet. The city's page still lays out the proposed terms beside the rules that apply without them.
- 2026-10-11
The council approved the agreement to annex the campus 5 to 0 on October 8th, under the written terms. The city's own campus page had not yet posted the result.
- 2026-10-15
CBS Austin's account of the council's vote still reads as cited. The city's own news post no longer answers at its address, so its wording is unconfirmed.
- 2026-10-18
CBS Austin's account of the council approving the annexation agreement still reads as cited. The city's own post did not answer, so its wording is unconfirmed.
- 2026-10-21
CBS Austin's account of the council approving the annexation agreement still reads as cited. The city's own news post now leads to a missing page, so its wording is unconfirmed.
- 2026-10-24
Taylor's annexation agreement for the data center campus is unconfirmed today, since the city's notice no longer answers at its old address.
- 2026-10-25
Taylor's annexation agreement for the data center campus stays unconfirmed on the city's notice, which no longer answers at its address. CBS Austin's report of the approval still reads as cited.
- 2026-10-26
Taylor's annexation agreement for the data center campus is still unconfirmed on the city's notice, which no longer answers. CBS Austin's report of the approval reads as cited.
- 2026-10-29
The city's campus page still carries the annexation agreement and its water, setback and noise terms. The earlier city notice has moved off its address.
- 2026-11-01
Taylor's annexation agreement for the data center campus still stands as approved on the city's record.
- 2026-11-05
Taylor's annexation agreement for the data center campus still reads as approved, its water and setback terms unchanged.
- 2026-11-08
Taylor's annexation agreement for the data center campus, with its water and setback terms, still reads as approved.
- 2026-11-12
Taylor's own page still sets out the annexation agreement and its written water and setback terms.
- 2026-11-15
Taylor's posted annexation agreement and its water and setback terms still read as cited.
- 2026-11-21
Taylor's annexation agreement for the data center campus, with its water, setback and noise terms, still reads as approved on the city's own campus page.
The evidence
Every fact above rests on one of these. The words are the source's own.
The City of Taylor is considering a proposed agreement with Big Watt Digital and PowerHouse Data Centers to move forward with annexation and development for Taylor Technology Campus, formerly known as Project Mustang, a 664-acre project that includes data center facilities and on-site power generation.City of Taylor, City considers proposed development agreement for Project Mustang development, posted October 2nd, 2026 Primary source, official · taylortx.gov
The proposed agreement will still go before City Council for a vote at the Oct. 8 City Council meeting.City of Taylor, City considers proposed development agreement for Project Mustang development, posted October 2nd, 2026 Primary source, official · taylortx.gov
This comes after the developers withdrew their annexation and zoning application with the City last month.City of Taylor, City considers proposed development agreement for Project Mustang development, posted October 2nd, 2026 Primary source, official · taylortx.gov
Without the development agreement, the project would have remained in unincorporated Williamson County, which has no zoning authority and minimal development regulations.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
The City of Taylor would have had no authority over any aspect of the project.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
The site will be designed and constructed with a closed loop cooling system utilizing reclaimed water with an initial fill volume of 1.575 million gallons for the entire site.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
No potable water will be authorized for use in filling the HVAC system or any need for evaporative cooling purposes unless a circumstance outlined in the agreement allowsCity of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
As part of the investments into the City’s wastewater system, the developers will withdraw their TCEQ wastewater discharge permit application.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
Buildings will be set back at least 300 feet from the north, east and west property lines.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
Along the south property line, data centers, power generation facilities and battery storage will be at least 700 feet from the property line, while accessory structures will be at least 500 feet away.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
A permanent landscaped buffer of at least 400 feet will also be provided along the south property line near FM 112.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
The buffer will include landscaped areas and earthen berms at least 6 feet high to provide additional screening.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
Air quality will be enforced by the Texas Commission on Environmental Quality (TCEQ).City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
Noise generated from the development shall not exceed the greater of either 65 dBA or the pre-development level.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
On-site emergency back-up generators are subject to monthly testing during weekdays between 8 a.m. and 5 p.m.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
In addition to these binding regulations, the developers are committing $28.2 million for community investments and nonprofit supportCity of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
The projected $1.38 billion in gross tax revenue generated by the project over 20 years could also provide the City with additional resources to invest in critical community prioritiesCity of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
The developers are not asking for any tax abatements with this request for development agreement approval.City of Taylor, Taylor Technology Campus Primary source, official · taylortx.gov
A major new data center project east of Taylor is moving forward after the City Council unanimously approved an agreement to annex the 664-acre development following months of heated debate and negotiations. The proposed agreement passed 5-0.CBS Austin, Taylor City Council greenlights 664-Acre Data Center Project, October 8th, 2026 Journalism · cbsaustin.com
Questions about this decision
Answered from the record itself. Every answer is assembled from stored fields, so an answer the record has no basis for is left out rather than guessed.
What is this decision?
The City of Taylor has a proposed development agreement with Big Watt Digital and PowerHouse Data Centers for Taylor Technology Campus. The 664 acre site was known as Project Mustang and includes data centers and on site power generation. The City Council approved the agreement 5 to 0 at its meeting on October 8th, 2026. The developers had withdrawn their annexation and zoning application with the city. The city's notice says the land would otherwise stay in unincorporated Williamson County, which has no zoning authority. Under the agreement the site is annexed and held to written terms. Cooling is a closed loop filled with reclaimed water, and potable water is barred from cooling except in circumstances the agreement names. Buildings sit at least 300 feet from the north, east and west lines. Data centers, generation and batteries sit at least 700 feet from the south line. Noise may not exceed the greater of 65 dBA or the level measured before construction. The developers commit $28.2 million for community investments and nonprofit support and ask for no tax abatement. Air quality stays with TCEQ.
Who decides it?
Taylor City Council decides. The record names the deciding body for every entry it carries.
Can the public take part?
The council approved the agreement on October 8th, 2026. The city's website carries archived meeting video.
Where in Texas does it apply?
It covers Williamson County in the Austin-Round Rock-San Marcos, TX area.
Has it been decided?
It has been decided. The dates on the item page carry when.
What happens next?
No future date is on the record. The last dated step on it was decided on October 8th.
When did it start?
The earliest date on its record is October 2nd, 2026.
What kind of decision is it?
It is filed under data centers.
What sources back it?
Three sources back it. Two of them are primary.
Is it on the ERCOT grid?
Yes. It sits inside the ERCOT interconnection.
When was it last checked?
Every fact on it was last verified against its source on November 21st, 2026.
Cite this
Texas AI Docket, Taylor City Council approves an agreement to annex a 664 acre data center campus under written water, setback and noise terms. Tracked since October 2nd, 2026. Last verified November 21st, 2026. https://texasaidocket.com/item/tx-2026-0203/. Reuse permitted under CC BY 4.0 with attribution. The same entry is in the docket JSON as item tx-2026-0203.
Beat
Filed under Data centers, with every other decision on that beat.